Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on the cross sectional area of R.C.C. or R.B. work) as per direction of Engineer-in-charge

Item number
15.5
Analysis basis
1 sqm
Priced inputs
3
Derived rate
₹1,147.20/ SQM
D-01/RATE ANALYSISITEM 15.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.5 (Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on the cross sectional area of R.C.C. or R.B. work) as per direction of Engineer-in-charge) is derived from 3 priced inputs for 1 sqm and works out to ₹1,147.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • R.C.C. or R.B. workReinforced area considering 1% reinforcement = 0.01sqm
  • For cutting 0.01 sqm reinforcement
ANALYSIS OF RATES · ITEM 15.5DETAIL OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.5816.00408.00
0114LABBeldarday0.5736.00368.00
9999MATSundriesL.S.13.392.2730.40
BUILD-UP TO RATE
TOTAL
806.40
Add 1 % Water charges on “W”
+8.06
TOTAL
814.46
Add GST on “X” (multiplying factor 0.2127)
+173.24
TOTAL
987.70
Add 15% CPOH on “Y”
+148.16
TOTAL
1,135.86
Add Cess @ 1% on “Z”
+11.36
Cost of 1.00 sqm
1,147.22
SAY
₹1,147.20
D-02/SOURCEPRINTED PAGE 1101
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1101

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1101. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.