Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-incharge

Item number
15.4
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹3,177.25/ CUM
D-01/RATE ANALYSISITEM 15.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.4 (Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-incharge) is derived from 3 priced inputs for 1 cum and works out to ₹3,177.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.4DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday2.12736.001,560.32
0115LABCoolieday0.9736.00662.40
9999MATSundriesL.S.4.682.2710.62
BUILD-UP TO RATE
TOTAL
2,233.34
Add 1 % Water charges on “W”
+22.33
TOTAL
2,255.67
Add GST on “X” (multiplying factor 0.2127)
+479.78
TOTAL
2,735.45
Add 15% CPOH on “Y”
+410.32
TOTAL
3,145.77
Add Cess @ 1% on “Z”
+31.46
Cost of 1.00 cum
3,177.23
SAY
₹3,177.25
D-02/SOURCEPRINTED PAGE 1100
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1100

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1100. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.