Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge

In lime mortar with old mughal bricks
Item number
15.7.2
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹1,783.35/ CUM
D-01/RATE ANALYSISITEM 15.7.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.7.2 (Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge In lime mortar with old mughal bricks) is derived from 3 priced inputs for 1 cum and works out to ₹1,783.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.7.2DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.24736.00912.64
0115LABCoolieday0.46736.00338.56
9999MATSundriesL.S.1.042.272.36
BUILD-UP TO RATE
TOTAL
1,253.56
Add 1 % Water charges on “W”
+12.54
TOTAL
1,266.10
Add GST on “X” (multiplying factor 0.2127)
+269.30
TOTAL
1,535.40
Add 15% CPOH on “Y”
+230.31
TOTAL
1,765.71
Add Cess @ 1% on “Z”
+17.66
Cost of 1.00 cum
1,783.37
SAY
₹1,783.35
D-02/SOURCEPRINTED PAGE 1102
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1102

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1102. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.