Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.9.1
- Analysis basis
- 1 cum
- Priced inputs
- 3
- Derived rate
- ₹1,158.10/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.9.1 (Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : In lime mortar) is derived from 3 priced inputs for 1 cum and works out to ₹1,158.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.61 | 736.00 | 448.96 |
| 0115 | LAB | Coolie | day | 0.49 | 736.00 | 360.64 |
| 9999 | MAT | Sundries | L.S. | 1.95 | 2.27 | 4.43 |
- TOTAL
- 814.03
- Add 1 % Water charges on “W”
- +8.14
- TOTAL
- 822.17
- Add GST on “X” (multiplying factor 0.2127)
- +174.88
- TOTAL
- 997.05
- Add 15% CPOH on “Y”
- +149.56
- TOTAL
- 1,146.61
- Add Cess @ 1% on “Z”
- +11.47
- Cost of 1.00 cum
- 1,158.08
- SAY
- ₹1,158.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1104
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1104. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.