Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured)

From brick work in cement mortar
Item number
15.8.3
Analysis basis
1000 Nos
Priced inputs
4
Derived rate
₹6,700.80/ NOS
D-01/RATE ANALYSISITEM 15.8.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.8.3 (Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in cement mortar) is derived from 4 priced inputs for 1000 Nos and works out to ₹6,700.80 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.8.3DETAIL OF COST FOR 1000 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday3.5736.002,576.00
0115LABCoolieday1.5736.001,104.00
0124LABMason 2nd classMason 2nd classday1.24816.001,011.84
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
4,710.14
Add 1 % Water charges on “W”
+47.10
TOTAL
4,757.24
Add GST on “X” (multiplying factor 0.2127)
+1,011.86
TOTAL
5,769.10
Add 15% CPOH on “Y”
+865.37
TOTAL
6,634.47
Add Cess @ 1% on “Z”
+66.34
Cost of 1000 Nos
6,700.81
SAY
₹6,700.80
D-02/SOURCEPRINTED PAGE 1104
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1104

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1104. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.