Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead

Thickness above 10 mm up to 25 mm
Item number
15.39.2
Analysis basis
10 sqm
Priced inputs
4
Derived rate
₹77.75/ SQM
D-01/RATE ANALYSISITEM 15.39.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.39.2 (Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead : Thickness above 10 mm up to 25 mm) is derived from 4 priced inputs for 10 sqm and works out to ₹77.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.39.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.25736.00184.00
0115LABCoolieday0.25736.00184.00
9999MATSundriesL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
546.55
Add 1 % Water charges on “W”
+5.47
TOTAL
552.02
Add GST on “X” (multiplying factor 0.2127)
+117.41
TOTAL
669.43
Add 15% CPOH on “Y”
+100.41
TOTAL
769.84
Add Cess @ 1% on “Z”
+7.70
Cost of 10.00 sqm
777.54
Cost of 1.00 sqm
77.75
SAY
₹77.75
D-02/SOURCEPRINTED PAGE 1123
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1123

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1123. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.