CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead

Up to 10 mm thick

Item number
15.39.1
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
61.00 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.39.1 Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead : Up to 10 mm thick — is derived from 4 priced inputs for 10 sqm and works out to ₹61.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0112Carpenter 2nd classLabourday0.15816.00122.40
0114BeldarLabourday0.2736.00147.20
0115CoolieLabourday0.2736.00147.20
9999SundriesMaterialL.S.5.332.2712.10
TOTAL
428.90
Add 1 % Water charges on “W”
4.29
TOTAL
433.19
Add GST on “X” (multiplying factor 0.2127)
92.14
TOTAL
525.33
Add 15% CPOH on “Y”
78.80
TOTAL
604.13
Add Cess @ 1% on “Z”
6.04
Cost of 10.00 sqm
610.17
Cost of 1.00 sqm
61.02
Say
61.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1122. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.