CPWD Analysis of Rates · Dismantling and Demolishing
Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge
- Item number
- 15.59
- Analysis basis
- Details of cost for 10 cum
- Priced inputs
- 4
- Derived rate
- ₹420.80 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.59 — Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge — is derived from 4 priced inputs for 10 cum and works out to ₹420.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0128 | MateLabour | day | 0.1 | 816.00 | 81.60 |
| 0114 | BeldarLabour | day | 3 | 736.00 | 2,208.00 |
| 0039 | Tractor with trolley .Tractor with trolleyMachinery | day | 0.475 | 1,350.00 | 641.25 |
| 0038 | Tractor with ripper attachment.Tractor with ripper attachmentMachinery | day | 0.02 | 1,350.00 | 27.00 |
- TOTAL
- 2,957.85
- Add 1 % Water charges on “W”
- 29.58
- TOTAL
- 2,987.43
- Add GST on “X” (multiplying factor 0.2127)
- 635.43
- TOTAL
- 3,622.86
- Add 15% CPOH on “Y”
- 543.43
- TOTAL
- 4,166.29
- Add Cess @ 1% on “Z”
- 41.66
- Cost of 10 cum
- 4,207.95
- Cost of 1 cum
- 420.80
- Say
- 420.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1141. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works