Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge
- Item number
- 15.59
- Analysis basis
- 10 cum
- Priced inputs
- 4
- Derived rate
- ₹420.80/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.59 (Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge) is derived from 4 priced inputs for 10 cum and works out to ₹420.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0128 | LAB | Mate | day | 0.1 | 816.00 | 81.60 |
| 0114 | LAB | Beldar | day | 3 | 736.00 | 2,208.00 |
| 0039 | MACH | Tractor with trolley .Tractor with trolley | day | 0.475 | 1,350.00 | 641.25 |
| 0038 | MACH | Tractor with ripper attachment.Tractor with ripper attachment | day | 0.02 | 1,350.00 | 27.00 |
- TOTAL
- 2,957.85
- Add 1 % Water charges on “W”
- +29.58
- TOTAL
- 2,987.43
- Add GST on “X” (multiplying factor 0.2127)
- +635.43
- TOTAL
- 3,622.86
- Add 15% CPOH on “Y”
- +543.43
- TOTAL
- 4,166.29
- Add Cess @ 1% on “Z”
- +41.66
- Cost of 10 cum
- 4,207.95
- Cost of 1 cum
- 420.80
- SAY
- ₹420.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1141
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1141. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate