Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge

Item number
15.59
Analysis basis
10 cum
Priced inputs
4
Derived rate
₹420.80/ CUM
D-01/RATE ANALYSISITEM 15.59

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.59 (Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge) is derived from 4 priced inputs for 10 cum and works out to ₹420.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.59DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0128LABMateday0.1816.0081.60
0114LABBeldarday3736.002,208.00
0039MACHTractor with trolley .Tractor with trolleyday0.4751,350.00641.25
0038MACHTractor with ripper attachment.Tractor with ripper attachmentday0.021,350.0027.00
BUILD-UP TO RATE
TOTAL
2,957.85
Add 1 % Water charges on “W”
+29.58
TOTAL
2,987.43
Add GST on “X” (multiplying factor 0.2127)
+635.43
TOTAL
3,622.86
Add 15% CPOH on “Y”
+543.43
TOTAL
4,166.29
Add Cess @ 1% on “Z”
+41.66
Cost of 10 cum
4,207.95
Cost of 1 cum
420.80
SAY
₹420.80
D-02/SOURCEPRINTED PAGE 1141
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1141

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1141. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.