CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge

Item number
15.59
Analysis basis
Details of cost for 10 cum
Priced inputs
4
Derived rate
420.80 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.59 Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge — is derived from 4 priced inputs for 10 cum and works out to ₹420.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0128MateLabourday0.1816.0081.60
0114BeldarLabourday3736.002,208.00
0039Tractor with trolley .Tractor with trolleyMachineryday0.4751,350.00641.25
0038Tractor with ripper attachment.Tractor with ripper attachmentMachineryday0.021,350.0027.00
TOTAL
2,957.85
Add 1 % Water charges on “W”
29.58
TOTAL
2,987.43
Add GST on “X” (multiplying factor 0.2127)
635.43
TOTAL
3,622.86
Add 15% CPOH on “Y”
543.43
TOTAL
4,166.29
Add Cess @ 1% on “Z”
41.66
Cost of 10 cum
4,207.95
Cost of 1 cum
420.80
Say
420.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1141. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.