Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead

Of area 3 sq. metres and below
Item number
15.12.1
Analysis basis
Detail of cost for each
Priced inputs
4
Derived rate
₹367.20
D-01/RATE ANALYSISITEM 15.12.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.12.1 (Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead : Of area 3 sq. metres and below) is derived from 4 priced inputs and works out to ₹367.20 after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.12.1DETAIL OF COST FOR EACH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0124LABMason 2nd classMason 2nd classday0.1816.0081.60
0114LABBeldarday0.18736.00132.48
0103LABBlacksmith 2nd classday0.05816.0040.80
9999MATSundriesL.S.1.432.273.25
BUILD-UP TO RATE
TOTAL
258.13
Add 1 % Water charges on “W”
+2.58
TOTAL
260.71
Add GST on “X” (multiplying factor 0.2127)
+55.45
TOTAL
316.16
Add 15% CPOH on “Y”
+47.42
TOTAL
363.58
Add Cess @ 1% on “Z”
+3.64
Cost of each
367.22
SAY
₹367.20
D-02/SOURCEPRINTED PAGE 1107
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1107

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1107. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.