CPWD Analysis of Rates · Dismantling and Demolishing

Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres

Above 150 mm diameter

Item number
15.53.2
Analysis basis
Detail of cost for dismantling 10 sluice valves
Priced inputs
4
Derived rate
1,184.15 / dismantling 10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.53.2 Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres Above 150 mm diameter — is derived from 4 priced inputs for dismantling 10 and works out to ₹1,184.15 per dismantling 10 after water charges, GST, CPOH and cess. The full build-up is below.

  • (ave.) 250mm
CodeInputUnitQuantityRate (INR)Amount (INR)
0116Fitter (grade 1)Labourday2.4897.002,152.80
0117Assistant Fitter or 2nd class FitterLabourday1.54816.001,256.64
0114BeldarLabourday6.4736.004,710.40
9999Sundries for removing the R.C.C. cover etc for dismantling sluice valveMaterialL.S.89.72.27203.62
TOTAL
8,323.46
Add 1 % Water charges on “W”
83.23
TOTAL
8,406.69
Add GST on “X” (multiplying factor 0.2127)
1,788.10
TOTAL
10,194.79
Add 15% CPOH on “Y”
1,529.22
TOTAL
11,724.01
Add Cess @ 1% on “Z”
117.24
Cost of 10 Nos
11,841.25
Cost of each
1,184.13
Say
1,184.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1136. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.