Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge

Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix)
Item number
15.2.2
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹1,503.60/ CUM
D-01/RATE ANALYSISITEM 15.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.2.2 (Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix)) is derived from 3 priced inputs for 1 cum and works out to ₹1,503.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 15.2.2DETAIL OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.88736.00647.68
0115LABCoolieday0.55736.00404.80
9999MATSundriesL.S.1.952.274.43
BUILD-UP TO RATE
TOTAL
1,056.91
Add 1 % Water charges on “W”
+10.57
TOTAL
1,067.48
Add GST on “X” (multiplying factor 0.2127)
+227.05
TOTAL
1,294.53
Add 15% CPOH on “Y”
+194.18
TOTAL
1,488.71
Add Cess @ 1% on “Z”
+14.89
Cost of 1.00 cum
1,503.60
SAY
₹1,503.60
D-02/SOURCEPRINTED PAGE 1099
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1099

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1099. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.