CPWD Analysis of Rates · Dismantling and Demolishing

Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge

Item number
15.48
Analysis basis
Details of cost for 1 man hole
Priced inputs
4
Derived rate
697.40 / man

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.48 Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge — is derived from 4 priced inputs for 1 man and works out to ₹697.40 per man after water charges, GST, CPOH and cess. The full build-up is below.

  • Demolition of R.C.C. slab 1.3x1.2x0.15 m
  • =0.234cum
  • Net Quantity =0.192cum
  • Less cover 0.61x0.455x0.15 m =0.042cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.5736.00368.00
0115CoolieLabourday0.14736.00103.04
9999Removel of C.I. Cover with frame including stackingMaterialL.S.1.32.272.95
9999SundriesMaterialL.S.7.152.2716.23
TOTAL
490.22
Add 1 % Water charges on “W”
4.90
TOTAL
495.12
Add GST on “X” (multiplying factor 0.2127)
105.31
TOTAL
600.43
Add 15% CPOH on “Y”
90.06
TOTAL
690.49
Add Cess @ 1% on “Z”
6.90
Cost of each
697.39
Say
697.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1133. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works