Skip to main content

Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge

Item number
15.48
Analysis basis
1 man
Priced inputs
4
Derived rate
₹697.40/ MAN
D-01/RATE ANALYSISITEM 15.48

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.48 (Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge) is derived from 4 priced inputs for 1 man and works out to ₹697.40 per man after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Demolition of R.C.C. slab 1.3x1.2x0.15 m
  • =0.234cum
  • Net Quantity =0.192cum
  • Less cover 0.61x0.455x0.15 m =0.042cum
ANALYSIS OF RATES · ITEM 15.48DETAILS OF COST FOR 1 MAN HOLE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.5736.00368.00
0115LABCoolieday0.14736.00103.04
9999MATRemovel of C.I. Cover with frame including stackingL.S.1.32.272.95
9999MATSundriesL.S.7.152.2716.23
BUILD-UP TO RATE
TOTAL
490.22
Add 1 % Water charges on “W”
+4.90
TOTAL
495.12
Add GST on “X” (multiplying factor 0.2127)
+105.31
TOTAL
600.43
Add 15% CPOH on “Y”
+90.06
TOTAL
690.49
Add Cess @ 1% on “Z”
+6.90
Cost of each
697.39
SAY
₹697.40
D-02/SOURCEPRINTED PAGE 1133
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1133

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1133. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDISMANTLING AND DEMOLISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.