CPWD Analysis of Rates · Dismantling and Demolishing
Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge
- Item number
- 15.49
- Analysis basis
- Detail of cost for 1 man hole
- Priced inputs
- 4
- Derived rate
- ₹406.75 / man
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.49 — Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work manually/ by mechanical means and stacking of useful materials near the site and disposal of unserviceable materials within 50 metres lead as per direction of Engineer-in-charge — is derived from 4 priced inputs for 1 man and works out to ₹406.75 per man after water charges, GST, CPOH and cess. The full build-up is below.
- Demolition of R.C.C. slab
- 1.1x0.9x0.15 m =0.148cum
- =0.106cum Say 0.11cum
- Less cover 0.61x0.455x0.15 m =0.042cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.29 | 736.00 | 213.44 |
| 0115 | CoolieLabour | day | 0.08 | 736.00 | 58.88 |
| 9999 | Removel of C.I. Cover with frame including stackingMaterial | L.S. | 0.65 | 2.27 | 1.48 |
| 9999 | SundriesMaterial | L.S. | 5.33 | 2.27 | 12.10 |
- TOTAL
- 285.90
- Add 1 % Water charges on “W”
- 2.86
- TOTAL
- 288.76
- Add GST on “X” (multiplying factor 0.2127)
- 61.42
- TOTAL
- 350.18
- Add 15% CPOH on “Y”
- 52.53
- TOTAL
- 402.71
- Add Cess @ 1% on “Z”
- 4.03
- Cost of each
- 406.74
- Say
- 406.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1133. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.