CPWD Analysis of Rates · Dismantling and Demolishing

Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per direction of Engineerin-charge

Item number
15.1
Analysis basis
Detail of cost for 1 cum
Priced inputs
3
Derived rate
851.50 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 15.1 Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per direction of Engineerin-charge — is derived from 3 priced inputs for 1 cum and works out to ₹851.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.44736.00323.84
0115CoolieLabourday0.37736.00272.32
9999SundriesMaterialL.S.1.042.272.36
TOTAL
598.52
Add 1 % Water charges on “W”
5.99
TOTAL
604.51
Add GST on “X” (multiplying factor 0.2127)
128.58
TOTAL
733.09
Add 15% CPOH on “Y”
109.96
TOTAL
843.05
Add Cess @ 1% on “Z”
8.43
Cost of 1.00 cum
851.48
Say
851.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1099. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.