Puducherry SOR 2024-25
Repair and Rehabilitation rates
12 repair and rehabilitation items from the Puducherry PWD, effective 2024-08-14.
Repair and Rehabilitation rates in the Puducherry Puducherry Schedule of Rates 2024-25 run from ₹91.23 to ₹3,665.37. Transcribed from Puducherry PWD — Puducherry Schedule of Rates 2024-25, Puducherry region. Base PDF only; PWD has since issued Correction Slip-3 (22 January 2025) for all four regions, so some rates here may be superseded.. Reference only — verify against the official source before pricing a bid.
12 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 16.1 | Removal of existing cement concrete wearing coat including its disposal complete as per technical specification without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all lifts and lead upto 1000m | Sqm | 193.60 |
| 16.2 | Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12mm thick mastic asphalt including disposal with all lift and lead upto 1000m | Sqm | 144.48 |
| 16.5A | Sealing of cracks / porous concrete by injection process through nipples/ grouting complete as per technical specifications- Cement grout | KG | 362.27 |
| 16.5B | Sealing of cracks / porous concrete by injection process through nipples / grouting complete as per technical specifications - cement mortar (1:1) grouting | KG | 406.63 |
| 16.7 | Sealing of crack / porous concrete with epoxy grout by injection through nipples complete as per clause 2803.1 | Sqm | 91.23 |
| 16.9 | Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, fine aggregate, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1, fine aggregate and coarse aggregates conforming to IS: 383 and Table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg / cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6 | Sqm | 419.30 |
| 16.11 | Epoxy bonding of new concrete to old concrete | Sqm | 659.00 |
| 16.17 | Replacement of expansion joints complete as per drawings | Rmt | 3,665.37 |
| 16.18 | Replacement of damaged concrete railing | Rmt | 687.15 |
| 16.19 | Replacement of crash barrier | Rmt | 1,329.03 |
| 16.20 | Replacement of damaged mild steel railing | Rmt | 558.77 |
| 16.21 | Repair of concrete crash barrier with cement concrete of M30 grade by cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired thorougly, applying cement concrete after erection of proper formwork | Rmt | 384.56 |
Other chapters in this schedule
- Earth Work (70)
- Concrete Work (72)
- Reinforced Concrete Work (131)
- Brick Work (57)
- Stone Work (50)
- Cladding Work (71)
- Wood and PVC Work (493)
- Steel Work (52)
- Flooring (91)
- Roofing (135)
- Finishing (114)
- Repairs To Buildings (108)
- Dismantling And Demolishing (85)
- Miscellaneous Building Work (25)
- Sanitary Installations (226)
- Water Supply (708)
- Drainage (135)
- Pile Work (31)
- Aluminium Work (41)
- Water Proofing (27)
- Rain Water Harvesting & TubeWells (37)
- Conservation of Heritage Buildings (7)
- Structural Glazing Aluminium Composite Panel (5)
- New Technologies and Materials (196)
- Irrigation (50)
- Water Supply (Public Health) (1012)
- Sewerage (Public Health) (213)
- Miscellaneous (Public Health) (71)
- OHT (Works) (8)
- Subsoil Exploration (7)
- Energy Conservation Building Code (137)
- Site Clearance and Dismantling (44)
- Earth Work, Erosion Control and Drainages (40)
- Granular Sub-base (63)
- Base & Bituminous Construction (26)
- Traffic Signs,Markings & Other Road Appurtenances (41)
- Pipe Culverts (5)
- Maintenance of Roads (13)
- Horticulture (25)
- Foundation (106)
- Substructure (54)
- Superstructure (97)
- River Training and Protection Works (10)
- PMGSY -Works (25)
Pricing repair and rehabilitation against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works