Pipe Culverts rates
- Items
- 5
- Lowest rate
- ₹5,826.22
- Highest rate
- ₹16,257.25
- Effective from
- 2024-08-14
Pipe Culverts rates in the Puducherry Puducherry Schedule of Rates 2024-25 run from ₹5,826.22 to ₹16,257.25. Transcribed from Puducherry PWD — Puducherry Schedule of Rates 2024-25, Puducherry region. Base PDF only; PWD has since issued Correction Slip-3 (22 January 2025) for all four regions, so some rates here may be superseded.. For reference only: verify against the official source before pricing a bid.
5 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 9.1 | Plain cement concrete 1:3:6 mix with crushed stone aggregate 40mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days | Cum | 5,826.22 |
| 9.2A | Laying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,concrete and masonry works in head walls and parapets-1000mm dia | Metre | 7,746.95 |
| 9.2B | Laying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,concrete and masonry works in head walls and parapets-1200mm dia | Metre | 8,022.98 |
| 9.3A | Laying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works back filling, concrete and masonry works in head walls and parapets - 1000mm. Dia | Metre | 15,691.10 |
| 9.3B | Laying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works back filling, concrete and masonry works in head walls and parapets - 1200mm. Dia | Metre | 16,257.25 |
- ISSUED BY
- Puducherry PWD
- EFFECTIVE
- 2024-08-14From the Puducherry PWD website, which lists this schedule as "PSR 2024-25 (with effect from 14th August 2024 onwards)". The PDF itself prints no date anywhere in its 1,216 pages.
- RETRIEVED
- 2026-07-29
Other chapters in this schedule
- Earth Work70
- Concrete Work72
- Reinforced Concrete Work131
- Brick Work57
- Stone Work50
- Cladding Work71
- Wood and PVC Work493
- Steel Work52
- Flooring91
- Roofing135
- Finishing114
- Repairs To Buildings108
SHOW ALL 44 CHAPTERS
- Dismantling And Demolishing85
- Miscellaneous Building Work25
- Sanitary Installations226
- Water Supply708
- Drainage135
- Pile Work31
- Aluminium Work41
- Water Proofing27
- Rain Water Harvesting & TubeWells37
- Conservation of Heritage Buildings7
- Structural Glazing Aluminium Composite Panel5
- New Technologies and Materials196
- Irrigation50
- Water Supply (Public Health)1012
- Sewerage (Public Health)213
- Miscellaneous (Public Health)71
- OHT (Works)8
- Subsoil Exploration7
- Energy Conservation Building Code137
- Site Clearance and Dismantling44
- Earth Work, Erosion Control and Drainages40
- Granular Sub-base63
- Base & Bituminous Construction26
- Traffic Signs,Markings & Other Road Appurtenances41
- Maintenance of Roads13
- Horticulture25
- Foundation106
- Substructure54
- Superstructure97
- River Training and Protection Works10
- Repair and Rehabilitation12
- PMGSY -Works25
Pricing pipe culverts against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.