Skip to main content

Puducherry SOR 2024-25

Pipe Culverts rates

5 pipe culverts items from the Puducherry PWD, effective 2024-08-14.

Pipe Culverts rates in the Puducherry Puducherry Schedule of Rates 2024-25 run from ₹5,826.22 to ₹16,257.25. Transcribed from Puducherry PWD — Puducherry Schedule of Rates 2024-25, Puducherry region. Base PDF only; PWD has since issued Correction Slip-3 (22 January 2025) for all four regions, so some rates here may be superseded.. Reference only — verify against the official source before pricing a bid.

5 items — scroll the table to browse

DescriptionUnit
9.1Plain cement concrete 1:3:6 mix with crushed stone aggregate 40mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 daysCum5,826.22
9.2ALaying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,concrete and masonry works in head walls and parapets-1000mm diaMetre7,746.95
9.2BLaying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,concrete and masonry works in head walls and parapets-1200mm diaMetre8,022.98
9.3ALaying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works back filling, concrete and masonry works in head walls and parapets - 1000mm. DiaMetre15,691.10
9.3BLaying reinforced cement concrete pipe Np4/ prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works back filling, concrete and masonry works in head walls and parapets - 1200mm. DiaMetre16,257.25

Pricing pipe culverts against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works