27 overhead lines& line materials items from the Board of Chief Engineers, Government of Andhra Pradesh, effective 2026-06-01.

Overhead Lines& Line Materials rates in the Andhra Pradesh Common Schedule of Rates — Part-III (Buildings, Water Supply & Electrical) 2026-27 run from ₹97.00 to ₹1,02,248.00. Transcribed from Government of Andhra Pradesh — Common Schedule of Rates 2026-27, Part-III (Buildings), Board of Chief Engineers. Reference only — verify against the official source before pricing a bid.

27 items — scroll the table to browse

DescriptionUnit
MAT-04090Supply and transportation of ………….PSCC Poles8.0 Mtr , Working load-140 KgsNos2,415.00
MAT-04091Supply and transportation of ………….PSCC Poles8.0 Mtr , Working load-200 KgsNos3,450.00
MAT-04092Supply and transportation of ………….PSCC Poles9.1 Mtr , Working load-280 KgsNos4,910.00
MAT-04093Supply and transportation of 9 mtr length ………….RS Joist Poles150 x 75 mm (Wt of the pole-140 Kgs)Nos10,500.00
MAT-04094Supply and transportation of 9 mtr length ………….RS Joist Poles175 x 85 mm (Wt of the pole-215Kgs)Nos16,125.00
MAT-04095Supply and transportation of 9 mtr length ………….RS Joist Poles150 x 150 mm (Wt of the pole-333 Kgs)Nos24,975.00
MAT-04096Supply and erection of GI stay set of dia……... including stay clamps, turn buckle and GI stay wire tight end through strain insulator including excavation of pit and cc work etc., complete20mm,2.4 mtr long stay rod and anchor plate 380mmx380mmx6.4mmSet2,245.00
MAT-04097Supply and erection of GI stay set of dia……... including stay clamps, turn buckle and GI stay wire tight end through strain insulator including excavation of pit and cc work etc., complete16mm,1.8 mtr long stay rod and anchor plate 380mmx380mmx6.4mmSet1,699.00
MAT-04098Supply and fixing of 11KV -V- cross arms with ……………...duly welded with necessary clamping arrangements etc., complete75x40 mm MS channel including 4 nos 50 x 50 x6 mm packing plates (9 Kgs)Nos1,494.00
MAT-04099Supply and fixing of 11KV -V- cross arms with ……………...duly welded with necessary clamping arrangements etc., complete65 x65 x6 MS angle (8.2 Kgs)Nos1,058.00
MAT-04100Supply and fixing of LT 3 phase 4 wire cross arm of length 3' 8" with……. and necessary clamping arrangements, cutting, drilling and welding etc., complete50 x 50 x6 mm MS angle ( wt 5.75 Kgs)Nos517.00
MAT-04101Supply and fixing of LT 3 phase 4 wire cross arm of length 3' 8" with……. and necessary clamping arrangements, cutting, drilling and welding etc., complete65 x65 x6 MS angle (wt 7 Kgs)Nos610.00
MAT-04102Supply and fixing of LT 3 phase 5 wire cross arm of length 4' 5" with……. and necessary clamping arrangements, cutting, drilling and welding etc., complete50 x 50 x6 mm MS angle ( wt 7.30Kgs)Nos667.00
MAT-04103Supply and fixing of LT 3 phase 5 wire cross arm of length 4' 5" with……. and necessary clamping arrangements, cutting, drilling and welding etc., complete65 x65 x6 MS angle (wt 9.60 Kgs)Nos841.00
MAT-04106Supply and fixing of ……... LT porcelain pin insulator as per IS 1447- 1997 suitable for working voltage 1100 V including all accessories like Hot dip GI spindle and nuts etc.,100 x 65 mmEach97.00
MAT-04107Supply and fixing of ……... LT porcelain pin insulator as per IS 1447- 1997 suitable for working voltage 1100 V including all accessories like Hot dip GI spindle and nuts etc.,100 x 85 mmEach109.00
MAT-04108Supply and fixing of ……... LT porcelain shackle insulator as per IS 1443-1979 suitable for working voltage 1100 V including all accessories like Hot dip GI spindle and nuts etc.,75 x 90 mmEach169.00
MAT-04109Supply and fixing of ……... LT porcelain shackle insulator as per IS 1443-1979 suitable for working voltage 1100 V including all accessories like Hot dip GI spindle and nuts etc.,100 x 110 mmEach206.00
MAT-04114Supply and Transportation of Over Head …………. Conductor as per IS 398 (PART - II): 1996100 Sq mm AAAKM1,02,248.00
MAT-04115Supply and Transportation of Over Head …………. Conductor as per IS 398 (PART - II): 199655 Sq mm AAAKM67,000.00
MAT-04116Supply and Transportation of Over Head …………. Conductor as per IS 398 (PART - II): 199634 Sq mm AAAKM36,000.00
ELEC-6.5.11Supply and fixing of distribution type lightning arrester 11 KV 5 kA as per IS 3070 with mounting base on the existing DP structureEach3,025.00
ELEC-6.5.12Supply and fixing of 100 A 11 KV Horn Gap fuse set as per IS 9385 on existing DP structure with 6 no of 24 KV /22 KV post Insulators (IS 5350, Hot dipped Hardware, fuse wire of required size etc., completeEach6,655.00
ELEC-6.5.13Supply and fixing of 11 KV danger plates on the existing polesEach121.00
ELEC-6.5.14Supply and fixing of 11 KV ,400 A 3 phase central post rotating double break type AB switch(isolator) as per IS 9921) without earth blade, gang operated, Horizontal type, operating mechanism with GI spring loaded reverse loop type fixed contact, solid HD electrolytic copper tubular moving contact with silver/Nickel plated at end points,9 Nos post insulators of 12 KV (IS 2594 and IS 5350) ,Hot Dip galvanizing hardware, GI pipe, Nuts and bolts etc., complete.,Each21,780.00
ELEC-6.5.20Providing transformer plinth 1.2 x 1.2 x 1.5 mtr in size with necessary excavation in ground at the bottom with 150mm thick 1:2:4 cement concrete raft at the bottom and top and 225mm thick wall constructed in stone masonry and remaking hallow portion shall be filled with stone chips duly plastered 20mm thick outsides including watering etc., completeNos12,100.00
ELEC-6.5.21Providing CTPT plinth 600mm x 600mm x 2.1 mtr in size with necessary excavation in ground at the bottom with 150mm thick 1:2:4 cement concrete raft at the bottom and top duly plastered 20mm thick outsides including watering etc., completeNos7,260.00

Other chapters in this schedule

Pricing overhead lines& line materials against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works