R/MAHARASHTRA SOR 2022-23
Rain water harvesting rates
9 rain water harvesting items from the Maharashtra Public Works Department (PWD), effective 2022-07-25.
- Items
- 9
- Lowest rate
- ₹339.00
- Highest rate
- ₹91,300.00
- Effective from
- 2022-07-25
S-01/RATE ITEMS9 ITEMS
Rain water harvesting rates in the Maharashtra State Schedule of Rates 2022-23 run from ₹339.00 to ₹91,300.00. Transcribed from Maharashtra PWD — State Schedule of Rates 2022-23, effective 25 July 2022. For reference only: verify against the official source before pricing a bid.
/
Unit
9 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 48.46 | RWH - Shallow Percolation Pit providing, constructing 2.0m deep shallow depth percolation pit comprising of 1.0m dia pre-cast RCC rings, 300mm thick side filling around outside of RCC rings (annular space) with 40mm size boulders including filling of percolation pit up to 0.5m depth (from bottom up) with 25-75mm clean washed gravels followed by 0.5m depth of 10-25mm of clean washed stones followed by 0.5m of washed river fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) including netlon mesh between each gravel/fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) media layer including covering with RCC slab, manhole frame & cover, PVC rungs etc. including arrangement for inlet & outlet pipe, excavation & backfilling as shown in the drawing. The rate shall be inclusive of all labour, material, wastage, scaffolding, transportation, taxes, including all leads, lifts at all levels. All material should be of approved make. All works complete as per the drawing, technical specification and direction of the Engineer in charge | Each | 51,500.00 |
| 48.47 | RWH - Recharge Pit Providing and constructing recharge pit of 2.0m deep and 1.0m dia of pre-cast RCC rings with 6.5" dia x 25m deep borewell at the floor of recharge pit including installation of combination of solid/perforated PVC casing pipe wrapped around with netlon mesh including 300mm thick sidefilling around outside of RCC rings (annular space) with 40mm size boulders including filling of recharge pit up to 0.5m depth with 25-75mm clean washed gravels from bottom up followed by 0.5m depth of 10- 25mm of clean washed stones followed by 0.5m of washed river fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) including netlon mesh between each gravel/fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) media layer including covering with RCC slab, manhole frame & cover, PVC rungs, PVC end- caps, fittings etc. including arrangement for inlet & outlet pipe excavation & backfilling as shown in the drawing.The rate shall be inclusive of all labour, material, wastage, scaffolding, transportation, taxes, including all leads, lifts at all levels. All material should be of approved make. All works complete as per the drawing, technical specification and direction of the Engineer in charge. | Each | 91,300.00 |
| 48.48 | Boring/drilling bore well of 300mm dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machinery required for the job, all complete as per direction of Engineer in charge, upto 90m depth below ground level. | Rmt | 416.00 |
| 48.49 | Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well-casing pipe of 150mm dia, conforming to IS:12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per the direction of Engineer in charge. | Rmt | 494.00 |
| 48.50 | Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well screen pipes with ribs of 100mm dia, conforming to IS:12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per the direction of Engineer in charge. | Each | 339.00 |
| 48.51 | Supplying, filling, spreading & leveling stone boulders of size range 5cm to 20cm in recharge pit, in the required thickness, for all leads & lifts, all complete as per the direction of Engineer- in-charge. | Cum | 1,309.00 |
| 48.52 | Supplying, filling, spreading & leveling gravels of size range 5mm to 10mm, in the recharge pit, over the existing layer of boulders, in required thickness, for all leads & lifts, all complete as per direction of Engineer-incharge. | Cum | 1,457.00 |
| 48.53 | Supplying, filling, spreading & leveling coarse fine aggregate (crushed sand VSI grade finely washed etc.) of size range 1.5mm to 2mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer in charge. | Cum | 1,457.00 |
| 48.54 | Gravel packing in tubewell construction in accordance with IS:4097, including providing gravel: fine/ medium/ coarse, in required grading & sizes as per the actual requirement, all complete as per direction of Engineer in charge. | Cum | 1,494.00 |
S-02/SOURCE RECORD2022-23
- ISSUED BY
- Maharashtra Public Works Department (PWD)
- EFFECTIVE
- 2022-07-25
- RETRIEVED
- 2026-07-29
S-03/CHAPTERS59 MORE
Other chapters in this schedule
- Road Survey and DPR76
- Road Sub grade36
- Road Sub Base and Base Course47
- Road Surfacing Course12
- Rigid Pavement23
- Road Furniture155
- Road Miscellaneous items34
- Road Maintenance39
- Cross Drainage Works28
- Bridge Foundation and Sub Structure40
- Bridge : Bored Pile51
- Bridge Bearings6
SHOW ALL 59 CHAPTERS
- Bridge Super Structure72
- Bridge : Bored Pile New Item18
- Bridge Maintenance19
- Bridge : Well Foundation24
- Bridge sub structure and Foundation28
- Bored Pile, Well Foundation, sub & Super Structure5
- Arch Bridge8
- Bridge Repair New Item46
- Excavation35
- Pile Foundation: Building57
- Structural Steel Work11
- Plain Cement Concrete9
- Reinforced Cement Concrete53
- Brick Masonry20
- Stone Masonry13
- Concrete Block Masonry9
- Expansion Joint11
- Water Proofing39
- Plastering and Pointing44
- Paving Flooring and dado78
- Wood Finish11
- Oil Painting29
- Colouring25
- Wood Work26
- Roofing and Ceiling57
- Roofing and Ceiling ( New Item)16
- Doors and Windows110
- Iron Work12
- Water Supply and Sanitary Fitting213
- Building Miscellaneous Item23
- Building Maintenance57
- Structural Strengthening16
- Flooring7
- Plumbing19
- Others7
- Coastal33
- Block masonary5
- Road work16
- Accoustic20
- Furniture39
- PWD persons28
- Cubical Toilet6
- Building7
- bambusa bamboos item7
- Bridge repair13
- Rebar29
- New Item18
ARCHED / ESTIMATING
Pricing rain water harvesting against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.