9 rain water harvesting items from the Maharashtra Public Works Department (PWD), effective 2022-07-25.
Rain water harvesting rates in the Maharashtra State Schedule of Rates 2022-23 run from ₹339.00 to ₹91,300.00. Transcribed from Maharashtra PWD — State Schedule of Rates 2022-23, effective 25 July 2022. Reference only — verify against the official source before pricing a bid.
9 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 48.46 | RWH - Shallow Percolation Pit providing, constructing 2.0m deep shallow depth percolation pit comprising of 1.0m dia pre-cast RCC rings, 300mm thick side filling around outside of RCC rings (annular space) with 40mm size boulders including filling of percolation pit up to 0.5m depth (from bottom up) with 25-75mm clean washed gravels followed by 0.5m depth of 10-25mm of clean washed stones followed by 0.5m of washed river fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) including netlon mesh between each gravel/fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) media layer including covering with RCC slab, manhole frame & cover, PVC rungs etc. including arrangement for inlet & outlet pipe, excavation & backfilling as shown in the drawing. The rate shall be inclusive of all labour, material, wastage, scaffolding, transportation, taxes, including all leads, lifts at all levels. All material should be of approved make. All works complete as per the drawing, technical specification and direction of the Engineer in charge | Each | 51,500.00 |
| 48.47 | RWH - Recharge Pit Providing and constructing recharge pit of 2.0m deep and 1.0m dia of pre-cast RCC rings with 6.5" dia x 25m deep borewell at the floor of recharge pit including installation of combination of solid/perforated PVC casing pipe wrapped around with netlon mesh including 300mm thick sidefilling around outside of RCC rings (annular space) with 40mm size boulders including filling of recharge pit up to 0.5m depth with 25-75mm clean washed gravels from bottom up followed by 0.5m depth of 10- 25mm of clean washed stones followed by 0.5m of washed river fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) including netlon mesh between each gravel/fine aggregate (natural sand/crushed sand VSI grade finely washed etc.) media layer including covering with RCC slab, manhole frame & cover, PVC rungs, PVC end- caps, fittings etc. including arrangement for inlet & outlet pipe excavation & backfilling as shown in the drawing.The rate shall be inclusive of all labour, material, wastage, scaffolding, transportation, taxes, including all leads, lifts at all levels. All material should be of approved make. All works complete as per the drawing, technical specification and direction of the Engineer in charge. | Each | 91,300.00 |
| 48.48 | Boring/drilling bore well of 300mm dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machinery required for the job, all complete as per direction of Engineer in charge, upto 90m depth below ground level. | Rmt | 416.00 |
| 48.49 | Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well-casing pipe of 150mm dia, conforming to IS:12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per the direction of Engineer in charge. | Rmt | 494.00 |
| 48.50 | Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well screen pipes with ribs of 100mm dia, conforming to IS:12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per the direction of Engineer in charge. | Each | 339.00 |
| 48.51 | Supplying, filling, spreading & leveling stone boulders of size range 5cm to 20cm in recharge pit, in the required thickness, for all leads & lifts, all complete as per the direction of Engineer- in-charge. | Cum | 1,309.00 |
| 48.52 | Supplying, filling, spreading & leveling gravels of size range 5mm to 10mm, in the recharge pit, over the existing layer of boulders, in required thickness, for all leads & lifts, all complete as per direction of Engineer-incharge. | Cum | 1,457.00 |
| 48.53 | Supplying, filling, spreading & leveling coarse fine aggregate (crushed sand VSI grade finely washed etc.) of size range 1.5mm to 2mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer in charge. | Cum | 1,457.00 |
| 48.54 | Gravel packing in tubewell construction in accordance with IS:4097, including providing gravel: fine/ medium/ coarse, in required grading & sizes as per the actual requirement, all complete as per direction of Engineer in charge. | Cum | 1,494.00 |
Other chapters in this schedule
- Road Survey and DPR (76)
- Road Sub grade (36)
- Road Sub Base and Base Course (47)
- Road Surfacing Course (12)
- Rigid Pavement (23)
- Road Furniture (155)
- Road Miscellaneous items (34)
- Road Maintenance (39)
- Cross Drainage Works (28)
- Bridge Foundation and Sub Structure (40)
- Bridge : Bored Pile (51)
- Bridge Bearings (6)
- Bridge Super Structure (72)
- Bridge : Bored Pile New Item (18)
- Bridge Maintenance (19)
- Bridge : Well Foundation (24)
- Bridge sub structure and Foundation (28)
- Bored Pile, Well Foundation, sub & Super Structure (5)
- Arch Bridge (8)
- Bridge Repair New Item (46)
- Excavation (35)
- Pile Foundation: Building (57)
- Structural Steel Work (11)
- Plain Cement Concrete (9)
- Reinforced Cement Concrete (53)
- Brick Masonry (20)
- Stone Masonry (13)
- Concrete Block Masonry (9)
- Expansion Joint (11)
- Water Proofing (39)
- Plastering and Pointing (44)
- Paving Flooring and dado (78)
- Wood Finish (11)
- Oil Painting (29)
- Colouring (25)
- Wood Work (26)
- Roofing and Ceiling (57)
- Roofing and Ceiling ( New Item) (16)
- Doors and Windows (110)
- Iron Work (12)
- Water Supply and Sanitary Fitting (213)
- Building Miscellaneous Item (23)
- Building Maintenance (57)
- Structural Strengthening (16)
- Flooring (7)
- Plumbing (19)
- Others (7)
- Coastal (33)
- Block masonary (5)
- Road work (16)
- Accoustic (20)
- Furniture (39)
- PWD persons (28)
- Cubical Toilet (6)
- Building (7)
- bambusa bamboos item (7)
- Bridge repair (13)
- Rebar (29)
- New Item (18)
Pricing rain water harvesting against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works