Ladakh SOR 2024
Pile Work rates
31 pile work items from the Ladakh Public Works (R&B), effective 2024-08-01.
Pile Work rates in the Ladakh Ladakh Schedule of Rates 2024 run from ₹1,421.54 to ₹26,128.38. Transcribed from UT of Ladakh, Public Works (R&B) Department — Ladakh Schedule of Rates (LSoR) 2024, Order No.58-LA-PW(R&B) of 2024 dated 24.07.2024, operative from 1 August 2024. Reference only — verify against the official source before pricing a bid.
31 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 20.1.1 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)400 mm dia piles | Metre | 2,933.24 |
| 20.1.2 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)450 mm dia piles | Metre | 3,620.78 |
| 20.1.3 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)500 mm dia piles | Metre | 4,399.96 |
| 20.1.4 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)550 mm dia piles | Metre | 4,828.36 |
| 20.1.5 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)750 mm dia piles | Metre | 8,306.92 |
| 20.1.6 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)1000 mm dia piles | Metre | 13,908.65 |
| 20.1.7 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)1200 mm dia piles | Metre | 18,236.98 |
| 20.1.8 | Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diametre and length below the pile cap M 25 in cement concrete, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)1500 mm dia piles | Metre | 26,128.38 |
| 20.2.1 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)300 mm dia piles | Metre | 1,421.54 |
| 20.2.2 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)450 mm dia piles | Metre | 2,452.48 |
| 20.2.3 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)500 mm dia piles | Metre | 3,084.12 |
| 20.2.4 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)550 mm dia. piles | Metre | 3,299.53 |
| 20.2.5 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)600 mm dia piles | Metre | 4,007.23 |
| 20.2.6 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)750 mm dia piles | Metre | 6,167.66 |
| 20.2.7 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)1000 mm dia piles | Metre | 10,908.28 |
| 20.2.8 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)1200 mm dia piles | Metre | 15,332.00 |
| 20.2.9 | Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diametre and length below the pile cap M 25 in cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be measured upto bottom of pile cap)1500 mm dia piles | Metre | 22,967.53 |
| 20.3.1 | Boring, Providing and installing cast in situ single under reamed piles of specified diametre and length below pile cap in M 25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto the bottom of pile cap)300 mm dia piles | Metre | 3,103.41 |
| 20.3.2 | Boring, Providing and installing cast in situ single under reamed piles of specified diametre and length below pile cap in M 25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto the bottom of pile cap)400 mm dia piles | Metre | 3,881.26 |
| 20.3.3 | Boring, Providing and installing cast in situ single under reamed piles of specified diametre and length below pile cap in M 25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto the bottom of pile cap)450 mm dia piles | Metre | 4,346.10 |
| 20.3.4 | Boring, Providing and installing cast in situ single under reamed piles of specified diametre and length below pile cap in M 25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto the bottom of pile cap)550 mm dia piles | Metre | 4,906.49 |
| 20.4.1 | Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified diametre (Only the quantity of extra bulbs are to be paid)300mm dia piles | Each | 2,384.03 |
| 20.4.2 | Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified diametre (Only the quantity of extra bulbs are to be paid)400mm dia piles | Each | 2,733.34 |
| 20.4.3 | Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified diametre (Only the quantity of extra bulbs are to be paid)450 mm dia piles | Each | 2,943.95 |
| 20.4.4 | Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified diametre (Only the quantity of extra bulbs are to be paid)550 mm dia piles | Each | 3,250.84 |
| 20.5.1 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)400 mm dia piles | Metre | 4,142.82 |
| 20.5.2 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)450 mm dia piles | Metre | 5,178.21 |
| 20.5.3 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)500 mm dia piles | Metre | 5,505.31 |
| 20.5.4 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)550 mm dia piles | Metre | 6,299.69 |
| 20.5.5 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)750 mm dia piles | Metre | 12,202.17 |
| 20.5.6 | Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diametre and length below the pile cap in M 25 cement concrete to carry safe working load not less than specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)1000 mm dia piles | Metre | 16,843.28 |
Other chapters in this schedule
- Earth work (40)
- Concrete Work (59)
- Reinforced Cement Concrete (106)
- Masonary Work (50)
- Stone Work (43)
- Cladding Work (49)
- Wood and PVC Work (342)
- Steel Work (53)
- Flooring Work (110)
- Roofing Work (123)
- Finishing Work (134)
- Repairs to Building (82)
- Dismantling and Demolishing (60)
- Road Work (121)
- Sanitary Installations (210)
- Water Supply (399)
- Drainage (68)
- Aluminium Work (33)
- Water Proofing (25)
- River and Canal Protection Work (8)
- Canal Lining Works (31)
- Slip Clearance (5)
- Rain Water Harvasting and Tube Wells (37)
- Conservation Of Heritage Building (7)
- Horticulture and Land Scaping (31)
- Structural Glazing Aluminium Composit Panel (5)
- New Technologies & Materials (166)
- Special Items for Ladakh (21)
Pricing pile work against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.