Ladakh SOR 2024
Canal Lining Works rates
31 canal lining works items from the Ladakh Public Works (R&B), effective 2024-08-01.
Canal Lining Works rates in the Ladakh Ladakh Schedule of Rates 2024 run from ₹25.81 to ₹1,11,031.17. Transcribed from UT of Ladakh, Public Works (R&B) Department — Ladakh Schedule of Rates (LSoR) 2024, Order No.58-LA-PW(R&B) of 2024 dated 24.07.2024, operative from 1 August 2024. Reference only — verify against the official source before pricing a bid.
31 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 24.1.1 | Lip-Cutting to desired profile for canal bed and sides, canal Including dressing, all allowances and leadsDepth upto 3.0 m | Cum | 467.13 |
| 24.1.2 | Lip-Cutting to desired profile for canal bed and sides, canal Including dressing, all allowances and leadsDepth over 3.0 m. but upto 4.5 m | Cum | 498.64 |
| 24.1.3 | Lip-Cutting to desired profile for canal bed and sides, canal Including dressing, all allowances and leadsDepth over 4.5 m. but upto 6.0 m | Cum | 483.99 |
| 24.1.4 | Lip-Cutting to desired profile for canal bed and sides, canal Including dressing, all allowances and leadsDepth over 6.0 m. but upto 7.5 m | Cum | 505.40 |
| 24.2.1 | Preparing and dressing beds of canals for liningIn ordinary soil | Sqm | 25.86 |
| 24.2.2 | Preparing and dressing beds of canals for liningIn soils admixed with up to 40% shingle / kankar / boulder 25.2.3 In soils | Sqm | 34.34 |
| 24.2.3 | Preparing and dressing beds of canals for liningAdmixed with more than 40% shingle / kankar / boulder | Sqm | 42.72 |
| 24.2.4 | Preparing and dressing beds of canals for liningIn mixed gravels/ conglomerate reaches | Sqm | 51.21 |
| 24.3.1 | Preparing and dressing side slopes of canals for liningIn ordinary soils | Sqm | 26.46 |
| 24.3.2 | Preparing and dressing side slopes of canals for liningIn soils admixed with up to 40% shingle / kankar / boulder | Sqm | 30.69 |
| 24.3.3 | Preparing and dressing side slopes of canals for liningIn soils admixed with more than 40% shingle / kankar / boulder | Sqm | 43.39 |
| 24.3.4 | Preparing and dressing side slopes of canals for liningIn mixed gravels/ conglomerate reaches | Sqm | 55.24 |
| 24.4 | Excavating conglomerate (for drains and bed-sleepers under the lining) | Cum | 1,534.32 |
| 24.5 | Making dry brick drains (behind lining), 75mm thick brick all around: only labour | Metre | 80.14 |
| 24.6 | Providing and laying 10mm thick, l cement: 3 fine sand mortar slurry' on beds and side slopes (prior to laying In-situ concrete lining) | Sqm | 132.36 |
| 24.7.1.1 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In bedsCrushed stone | Cum | 7,838.61 |
| 24.7.1.2 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In bedsNallah Stone | Cum | 8,025.46 |
| 24.7.2.1 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, - upto a height of 3.5 m above bedCrushed stone | Cum | 8,355.73 |
| 24.7.2.2 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, - upto a height of 3.5 m above bedNallah Stone | Cum | 8,009.30 |
| 24.7.3.1 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, - at a height over 3.5 m but upto 5.5m above bedCrushed stone | Cum | 8,016.37 |
| 24.7.3.2 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, - at a height over 3.5 m but upto 5.5m above bedNallah Stone | Cum | 7,705.29 |
| 24.7.4.1 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, at heights over 5.5 m but upto 7.5 m above bedCrushed stone | Cum | 8,140.60 |
| 24.7.4.2 | Providing and laying in-situ concrete lining using M-10 nominal mix concrete (max. size of aggregates: 20mm nominal) — In side slopes, at heights over 5.5 m but upto 7.5 m above bedNallah Stone | Cum | 7,838.61 |
| 24.8.1 | Curing canal lining for 28 daysIn beds | Sqm | 25.81 |
| 24.8.2 | Curing canal lining for 28 daysIn side slopes | Sqm | 76.19 |
| 24.9.1 | Flush pointing in 1 cement: 3 fine sand mortarIn beds of canal linings | Sqm | 236.35 |
| 24.9.2 | Flush pointing in 1 cement: 3 fine sand mortarIn side slopes of canal linings | Sqm | 244.81 |
| 24.10 | Filling expansion joints (12mm wide) with special Impervious hot-pour | Cum | 1,11,031.17 |
| 24.11 | Extra over Item nallah lining towards allowance for form-work | Sqm | 340.77 |
| 24.12 | Extra over item no.3.5 m above height owards allowance for form-work | Sqm | 448.54 |
| 24.13 | Extra over item towards allowance for providing templates In curved portion; area of curved portion to be measured | Sqm | 60.35 |
Other chapters in this schedule
- Earth work (40)
- Concrete Work (59)
- Reinforced Cement Concrete (106)
- Masonary Work (50)
- Stone Work (43)
- Cladding Work (49)
- Wood and PVC Work (342)
- Steel Work (53)
- Flooring Work (110)
- Roofing Work (123)
- Finishing Work (134)
- Repairs to Building (82)
- Dismantling and Demolishing (60)
- Road Work (121)
- Sanitary Installations (210)
- Water Supply (399)
- Drainage (68)
- Pile Work (31)
- Aluminium Work (33)
- Water Proofing (25)
- River and Canal Protection Work (8)
- Slip Clearance (5)
- Rain Water Harvasting and Tube Wells (37)
- Conservation Of Heritage Building (7)
- Horticulture and Land Scaping (31)
- Structural Glazing Aluminium Composit Panel (5)
- New Technologies & Materials (166)
- Special Items for Ladakh (21)
Pricing canal lining works against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works