Rajasthan SOR 2025-26
Road Works: Site Clearance rates
62 road works: site clearance items from the Rajasthan PWD (Roads & Bridges), effective 2025-04-01.
Road Works: Site Clearance rates in the Rajasthan Basic Schedule of Rates 2025-26 run from ₹5.75 to ₹44,350.00. Transcribed from Rajasthan PWD — Unified Basic Schedule of Rates for year 2025-26, Road & Bridge Works (other than NH & PMGSY), Chief Engineer (Roads), P.W.D. Rajasthan, Jaipur; effective from 01-04-2025. Reference only — verify against the official source before pricing a bid.
62 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| R-2.2(I)(A) | Clearing and Grubbing Road Land By Manual MeansIn area of non-thorny jungle | Hectare | 33,075.00 |
| R-2.2(I)(B) | Clearing and Grubbing Road Land By Manual MeansIn area of thorny jungle | Hectare | 44,350.00 |
| R-2.2(II)(A) | Clearing and Grubbing Road Land By Mechanical MeansIn area of non-thorny jungle | Hectare | 12,513.00 |
| R-2.2(II)(B) | Clearing and Grubbing Road Land By Mechanical MeansIn area of thorny jungle | Hectare | 15,386.00 |
| R-2.3(A)(i) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 300 mm to 600 mm | Each | 145.00 |
| R-2.3(A)(ii) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 600 mm to 900 mm | Each | 250.00 |
| R-2.3(A)(iii) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 900 mm to 1800 mm | Each | 510.00 |
| R-2.3(A)(iv) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 1800 mm to 2700 mm | Each | 984.00 |
| R-2.3(A)(v) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 2700 mm to 4500 mm | Each | 2,050.00 |
| R-2.3(A)(vi) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 100 mGirth above 4500 mm | Each | 6,083.00 |
| R-2.3(B)(i) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 300 mm to 600 mm | Each | 151.00 |
| R-2.3(B)(ii) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 600 mm to 900 mm | Each | 277.00 |
| R-2.3(B)(iii) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 900 mm to 1800 mm | Each | 555.00 |
| R-2.3(B)(iv) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 1800 mm to 2700 mm | Each | 1,049.00 |
| R-2.3(B)(v) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 2700 mm to 4500 mm | Each | 2,112.00 |
| R-2.3(B)(vi) | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps Lead upto 1000 mGirth above 4500 mm | Each | 6,230.00 |
| R-2.4(A)(i) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 300 mm to 600 mm | Each | 81.00 |
| R-2.4(A)(ii) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 600 mm to 900 mm | Each | 132.00 |
| R-2.4(A)(iii) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 900 mm to 1800 mm | Each | 308.00 |
| R-2.4(A)(iv) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 1800 mm to 2700 mm | Each | 595.00 |
| R-2.4(A)(v) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 2700 mm to 4500 mm | Each | 1,230.00 |
| R-2.4(A)(vi) | Uprooting and Removing Stumps & Roots Lead upto 100 mGirth above 4500 mm | Each | 3,505.00 |
| R-2.4(B)(i) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 300 mm to 600 mm | Each | 81.00 |
| R-2.4(B)(ii) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 600 mm to 900 mm | Each | 145.00 |
| R-2.4(B)(iii) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 900 mm to 1800 mm | Each | 308.00 |
| R-2.4(B)(iv) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 1800 mm to 2700 mm | Each | 616.00 |
| R-2.4(B)(v) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 2700 mm to 4500 mm | Each | 1,245.00 |
| R-2.4(B)(vi) | Uprooting and Removing Stumps & Roots Lead upto 1000 mGirth above 4500 mm | Each | 3,590.00 |
| R-2.5(I)(A) | Dismantling of Structures By Manual MeansLime Concrete | Cum | 225.00 |
| R-2.5(I)(B) | Dismantling of Structures By Manual MeansCement Concrete | Cum | 305.00 |
| R-2.5(I)(C) | Dismantling of Structures By Manual MeansReinforced Cement Concrete | Cum | 708.00 |
| R-2.5(II)(A) | Dismantling of Structures By Mechanical MeansCement Concrete | Cum | 308.00 |
| R-2.5(II)(B) | Dismantling of Structures By Mechanical MeansReinforced Cement Concrete | Cum | 478.00 |
| R-2.6(A) | Dismantling Brick/Tile WorkLime mortar | Cum | 145.00 |
| R-2.6(B) | Dismantling Brick/Tile WorkCement mortar | Cum | 195.00 |
| R-2.6(C) | Dismantling Brick/Tile WorkMud Mortar | Cum | 119.00 |
| R-2.6(D) | Dismantling Brick/Tile WorkDry Brick Pitching or Brick Soling | Cum | 118.00 |
| R-2.7(A) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Rubble Stone Masonry in Lime Mortar | Cum | 162.00 |
| R-2.7(B) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Rubble Stone Masonry in Cement Mortar | Cum | 195.00 |
| R-2.7(C) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Rubble Stone Masonry in Mud Mortar | Cum | 145.00 |
| R-2.7(D) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Dry Rubble Masonry | Cum | 132.00 |
| R-2.7(E) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Dismantling Stone Pitching / Dry Stone Spalls | Cum | 118.00 |
| R-2.7(F) | Dismantling Stone Masonry as per MoRTH Specification Clause 202Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials | Cum | 151.00 |
| R-2.8 | Dismantling Wood Work Wrought and Planed Fixed in Frames of Trusses upto a height of 5 m above Plinth Level as per MoRTH Specification Clause 202 | Cum | 348.00 |
| R-2.9(A) | Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth Level excluding Cutting of rivet as per MoRTH Specification Clause 202Including dismembering | Tonne | 939.00 |
| R-2.9(B) | Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth Level excluding Cutting of rivet as per MoRTH Specification Clause 202Excluding dismembering | Tonne | 649.00 |
| R-2.9(C) | Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth Level excluding Cutting of rivet as per MoRTH Specification Clause 202Extra over Items (A) and (B) for cutting rivets | Tonne | 5.75 |
| R-2.11 | Scraping of Stone from Dismantled Stone Masonry as per MoRTH Specification Clause 202In Cement or Lime Mortar | Cum | 302.00 |
| R-2.12 | Scraping Plaster in Lime or Cement Mortar from Brick / Stone Masonry as per MoRTH Specification Clause 202 | Sqm | 8.50 |
| R-2.14(I)(A) | Dismantling of Flexible Pavements By Manual MeansBituminous Courses | Cum | 445.00 |
| R-2.14(I)(B) | Dismantling of Flexible Pavements By Manual MeansGranular Courses | Cum | 312.00 |
| R-2.14(II)(A) | Dismantling of Flexible Pavements By Mechanical MeansBituminous Courses & Granular Courses | Cum | 100.00 |
| R-2.15 | Dismantling of Cement Concrete Pavements as per MoRTH Specification Clause 202Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately | Cum | 632.00 |
| R-2.16 | Dismantling Guard RailsDismantling guard rails by manual means and disposal of dismantled material with all lifts and upto a lead of 1000 m, stacking serviceable materials and unserviceable materials separately as per MoRTH Specification Clause 202 | Rmt | 44.00 |
| R-2.17 | Dismantling Kerb StonesDismantling kerb stones by manual means and disposal of dismantled material with all lifts and upto a lead of 1000 m as per MoRTH Specification Clause 202 | Rmt | 8.00 |
| R-2.18 | Dismantling Kerb Stone ChannelsDismantling kerb stone channels by manual means and disposal of dismantled material with all lifts and upto a lead of 1000 m as per MoRTH Specification Clause 202 | Rmt | 12.75 |
| R-2.19(A) | Dismantling Kilometre Stones5th km Stone | Rmt | 202.00 |
| R-2.19(B) | Dismantling Kilometre StonesOrdinary km Stones | Rmt | 118.00 |
| R-2.19(C) | Dismantling Kilometre Stones200 m Stones | Rmt | 25.00 |
| R-2.20 | Dismantling of FencingDismantling of barbed wire fencing / wire mesh fencing including posts, foundation concrete, backfilling of pit by manual means including disposal of dismantled material with all lifts and upto a lead of 1000 m, stacking serviceable material and unserviceable material separately as per MoRTH Specification Clause 202 | Rmt | 31.00 |
| R-2.21 | Dismantling of CI Water Pipe LineDismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 m and stacking of serviceable material and unserviceable material separately under supervision of concerned department as per MoRTH Specification Clause 202 | Rmt | 94.00 |
| R-2.22 | Removal of Cement Concrete Pipe of Sewer GutterRemoval of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and upto a lead of 1000 m and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works as per MoRTH Specification Clause 202 | Rmt | 106.00 |
Other chapters in this schedule
- Road Works: Loading, Unloading, Carriage Crushing of Materials and Setting (24)
- Road Works: Earthwork, Erosion Control and Drainage (28)
- Road Works: Granular Sub-Bases, Bases (Non-Bituminous) and Shoulders (21)
- Road Works: Bases and Surface Courses (Bituminous) (13)
- Road Works: Cement Concrete Pavement (32)
- Road Works: Pipe Culverts (16)
- Road Works: Traffic Signs, Markings and Other Road Appurtenances (60)
- Road Works: Foundation (31)
- Road Works: Substructure (36)
- Road Works: Superstructure (32)
- Road Works: Protection Works (20)
- Road Works: Maintenance of Roads (28)
- Road Works: Additional Items (101)
- Road Works: Additional Items (New) (307)
- Bridge Works: Earthwork for Bridges (17)
- Bridge Works: Foundation (85)
- Bridge Works: Substructure (38)
- Bridge Works: Super Structure (39)
- Bridge Works: Protective Works (8)
- Bridge Works: Repair and Rehabilitation (6)
Pricing road works: site clearance against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works