16 road works: pipe culverts items from the Rajasthan PWD (Roads & Bridges), effective 2025-04-01.
Items
16
Lowest rate
₹736.00
Highest rate
₹15,711.00
Effective from
2025-04-01
S-01/RATE ITEMS16 ITEMS

Road Works: Pipe Culverts rates in the Rajasthan Basic Schedule of Rates 2025-26 run from ₹736.00 to ₹15,711.00. Transcribed from Rajasthan PWD — Unified Basic Schedule of Rates for year 2025-26, Road & Bridge Works (other than NH & PMGSY), Chief Engineer (Roads), P.W.D. Rajasthan, Jaipur; effective from 01-04-2025. For reference only: verify against the official source before pricing a bid.

Download the full schedule (Excel)All 22 chapters

16 items. Scroll the table to browse

DescriptionUnit
R-9.3(A)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row1200 mm diaRmt6,684.00
R-9.3(B)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row1000 mm diaRmt4,643.00
R-9.3(C)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row750 mm diaRmt3,298.00
R-9.3(D)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row600 mm diaRmt1,941.00
R-9.3(E)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row300 mm diaRmt736.00
R-9.4(A)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single Row1200 mm diaRmt7,828.00
R-9.4(B)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single Row1000 mm diaRmt5,420.00
R-9.4(C)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single Row750 mm diaRmt3,629.00
R-9.5(A)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in Double Row1200 mm diaRmt13,402.00
R-9.5(B)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in Double Row1000 mm diaRmt9,317.00
R-9.5(C)Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in Double Row750 mm diaRmt6,595.00
R-9.6(A)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in Double Row1200 mm diaRmt15,711.00
R-9.6(B)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in Double Row1000 mm diaRmt10,873.00
R-9.6(C)Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in Double Row750 mm diaRmt7,256.00
R-9.7Laying Cement Concrete Pipe NP3 (burried conduits) on first class bedding of granular material including fixing collar with cement sand mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonary work in head wall and parapets as per Clause 2905500 mm diaRmt746.00
R-9.8Laying Cement Concrete Pipe NP4 (burried conduits) on first class bedding of granular material including fixing collar with cement sand mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonary work in head wall and parapets as per Clause 2905500 mm diaRmt1,111.00
S-02/SOURCE RECORD2025-26
ISSUED BY
Rajasthan PWD (Roads & Bridges)
EFFECTIVE
2025-04-01
RETRIEVED
2026-07-29
S-03/CHAPTERS20 MORE

Other chapters in this schedule

SHOW ALL 20 CHAPTERS
ARCHED / ESTIMATING

Pricing road works: pipe culverts against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.