Bridge Works: Earthwork for Bridges rates

17 bridge works: earthwork for bridges items from the Rajasthan PWD (Roads & Bridges), effective 2025-04-01.

Bridge Works: Earthwork for Bridges rates in the Rajasthan Basic Schedule of Rates 2025-26 run from ₹190.00 to ₹780.00. Transcribed from Rajasthan PWD — Unified Basic Schedule of Rates for year 2025-26, Road & Bridge Works (other than NH & PMGSY), Chief Engineer (Roads), P.W.D. Rajasthan, Jaipur; effective from 01-04-2025. Reference only — verify against the official source before pricing a bid.

17 items — scroll the table to browse

DescriptionUnit
B-1.1.1In ordinary soil Depth upto 3 metreDepth upto 3 metreCum190.00
B-1.1.2In ordinary soil Depth upto 3 metreDepth above 3 metre & upto 6 metreCum225.00
B-1.1.2.1In ordinary soil Depth upto 3 metre In hard soilDepth upto 3 metreCum252.00
B-1.1.2.2In ordinary soil Depth upto 3 metre In hard soilDepth above 3 metre & upto 6 metreCum297.00
B-1.1.2.3In ordinary soil Depth upto 3 metre In hard soilDepth above 6 metreCum340.00
B-1.1.3In ordinary soil Depth upto 3 metreDepth above 6 metreCum275.00
B-1.1.3.1In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. upto 20%Depth upto 3 metreCum275.00
B-1.1.3.2In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. upto 20%Depth above 3 metre & upto 6 metreCum340.00
B-1.1.3.3In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. upto 20%Depth above 6 metreCum430.00
B-1.1.4.1In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. above 20%Depth upto 3 metreCum350.00
B-1.1.4.2In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. above 20%Depth above 3 metre & upto 6 metreCum430.00
B-1.1.4.3In ordinary soil Depth upto 3 metre In hard soil mixed with kankar,boulders etc. above 20%Depth above 6 metreCum530.00
B-1.1.7In ordinary soil Depth upto 3 metreIn marshy soil upto 3 metre depthCum382.00
B-1.2Sand filling with compaction in wells complete as per drawing and technical specification as per MoRTH Specification : Section 1210Cum660.00
B-1.3.1Back filling behind abutment, wing wall and return wall in 150mm layers, with mechanical compaction, complete with all lead and lift as per drawing and technical specification as per MoRTH Specification : Clause : 304Gravelly materialCum604.00
B-1.3.2Back filling behind abutment, wing wall and return wall in 150mm layers, with mechanical compaction, complete with all lead and lift as per drawing and technical specification as per MoRTH Specification : Clause : 304Sandy materialCum350.00
B-1.4Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRT&H specifications with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification including all material, labour, machinery as per clause 710.1.4 of IRC:78 and clause 2200 of MoRT&H specificationCum780.00

Pricing bridge works: earthwork for bridges against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.