S-01/RATE ITEMS31 ITEMS
Road Works: Foundation rates in the Rajasthan Basic Schedule of Rates 2025-26 run from ₹118.00 to ₹93,000.00. Transcribed from Rajasthan PWD — Unified Basic Schedule of Rates for year 2025-26, Road & Bridge Works (other than NH & PMGSY), Chief Engineer (Roads), P.W.D. Rajasthan, Jaipur; effective from 01-04-2025. For reference only: verify against the official source before pricing a bid.
/
Unit
31 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| R-11.1(I)(ii) | Excavation for Structures Ordinary soil3 m to 6 m depth | Cum | 212.00 |
| R-11.1(III) | Excavation for StructuresHard rock (requiring blasting) | Cum | 398.00 |
| R-11.1(IV) | Excavation for StructuresHard rock (blasting prohibited) | Cum | 400.00 |
| R-11.1(V) | Excavation for StructuresMarshy soil | Cum | 334.00 |
| R-11.2(I) | Fillling in foundation trenches as per drawing and MoRTH specification Clause 304.3.7Sand filling | Cum | 946.00 |
| R-11.2(II) | Fillling in foundation trenches as per drawing and MoRTH specification Clause 304.3.7Earth filling (For marshy soil) | Cum | 118.00 |
| R-11.3 | Filling annular space around footing in rock as per MoRTH specification Clause 2104.3Nominal mix 1:2.5:5 | Cum | 4,088.00 |
| R-11.4(I)(i) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 10Nominal mix 1:3:6 | Cum | 3,091.00 |
| R-11.4(I)(ii) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 10Nominal mix 1:3.6 (Hand mixing) | Cum | 3,030.00 |
| R-11.4(II)(i) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 15Nominal mix (1:2.5:5) | Cum | 3,334.00 |
| R-11.4(II)(ii) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 15Nominal mix 1:2.5:5 (Hand mixing) | Cum | 3,270.00 |
| R-11.4(III)(i) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C. grade M 20Nominal mix (1:2:4) | Cum | 3,515.00 |
| R-11.4(III)(ii) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C. grade M 20Nominal mix 1:2:4 (Hand mixed) | Cum | 3,479.00 |
| R-11.4(IV) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104R.C.C grade M 20 | Cum | 3,577.00 |
| R-11.4(V) | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104R.C.C. grade M 25 | Cum | 3,940.00 |
| R-11.5(I) | Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and MoRTH specifications Clauses 1300, 2102 & 2104Brick masonry in 1:3 cement mortar | Cum | 4,293.00 |
| R-11.5(II) | Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and MoRTH specifications Clauses 1300, 2102 & 2104Brick masonry in 1:4 cement mortar | Cum | 3,985.00 |
| R-11.5(III) | Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and MoRTH specifications Clauses 1300, 2102 & 2104Brick masonry in cement-lime-mortar (1:0.5:4.5) | Cum | 4,315.00 |
| R-11.6(I)(i) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (1st sort)In 1:3 cement mortar | Cum | 4,062.00 |
| R-11.6(I)(ii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (1st sort)In 1:4 cement mortar | Cum | 3,674.00 |
| R-11.6(I)(iii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (1st sort)In cement-lime-sand mortar (1:0.5:4.5) | Cum | 4,074.00 |
| R-11.6(II)(i) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (2nd sort)In 1:3 cement mortar | Cum | 3,601.00 |
| R-11.6(II)(ii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (2nd sort)In 1:4 cement mortar | Cum | 2,764.00 |
| R-11.6(II)(iii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Coursed rubble masonry (2nd sort)In cement-lime-mortar (1:0.5:4.5) | Cum | 3,189.00 |
| R-11.6(III)(i) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Random Rubble MasonryIn 1:3 cement mortar | Cum | 3,420.00 |
| R-11.6(III)(ii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Random Rubble MasonryIn 1:4 cement mortar | Cum | 2,994.00 |
| R-11.6(III)(iii) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Random Rubble MasonryIn 1:6 cement mortar | Cum | 2,480.00 |
| R-11.6(III)(iv) | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. Random Rubble MasonryIn cement lime mortar (1:0.5:4.5) | Cum | 3,635.00 |
| R-11.7 | Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and MoRTH specifications Clauses 1009,1600 and 2102 | Tonne | 92,000.00 |
| R-11.8 | Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and MoRTH specifications Clauses 1009,1600 and 2102 | Tonne | 93,000.00 |
| R-11.9 | Supplying, fitting and placing MS bar reinforcement in foundation complete as per drawings and MoRTH specifications Clauses 1009,1600 and 2102 | Tonne | 91,000.00 |
S-02/SOURCE RECORD2025-26
- ISSUED BY
- Rajasthan PWD (Roads & Bridges)
- EFFECTIVE
- 2025-04-01
- RETRIEVED
- 2026-07-29
S-03/CHAPTERS20 MORE
Other chapters in this schedule
- Road Works: Loading, Unloading, Carriage Crushing of Materials and Setting24
- Road Works: Site Clearance62
- Road Works: Earthwork, Erosion Control and Drainage28
- Road Works: Granular Sub-Bases, Bases (Non-Bituminous) and Shoulders21
- Road Works: Bases and Surface Courses (Bituminous)13
- Road Works: Cement Concrete Pavement32
- Road Works: Pipe Culverts16
- Road Works: Traffic Signs, Markings and Other Road Appurtenances60
- Road Works: Substructure36
- Road Works: Superstructure32
- Road Works: Protection Works20
- Road Works: Maintenance of Roads28
ARCHED / ESTIMATING
Pricing road works: foundation against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.