8 pcc work with plum items from the Assam Water Resources Department, effective 2023-04-01.

PCC Work with Plum rates in the Assam Civil Works Schedule of Rates 2023-24 run from ₹6,137.69 to ₹7,658.98. Transcribed from Assam Water Resources (Irrigation) Department — Schedule of Rates (Civil Works) 2023-24. Reference only — verify against the official source before pricing a bid.

8 items — scroll the table to browse

DescriptionUnit
11.1 (A)(i)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD BLASTED BOULDERPlain CC work in 40% plum hard blasted boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size stone aggregate including curing, shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum7,275.34
11.1 (A)(ii)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD BLASTED BOULDERPlain CC work in 40% plum hard blasted boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size stone aggregate including curing, dewatering shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum7,658.98
11.1 (A)(iii)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD BLASTED BOULDERPlain CC work in 40% plum hard blasted boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size river shingles including curing, shuttering etc, complete as directed. (Cost of shuttering will be paid separately)Cum6,387.06
11.1 (A)(iv)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD BLASTED BOULDERPlain CC work in 40% plum hard blasted boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size river shingles including curing, dewatering, shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum6,770.71
11.1 (B)(i)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD RIVER BOULDERPlain CC work in 40% plum hard river boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size river shingles including curing, shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum6,137.69
11.1 (B)(ii)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD RIVER BOULDERPlain CC work in 40% plum hard river boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size river shingles including curing, dewatering, shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum6,521.34
11.1 (B)(iii)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD RIVER BOULDERPlain CC work in 40% plum hard river boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size stone aggregate including curing, shuttering etc. complete as directed. (Shuttering cost will be paid separately)Cum7,025.97
11.1 (B)(iv)PLAIN CC WORK WITH 40% PLUM HARD BOULDER IN PROPORTION — WITH HARD RIVER BOULDERPlain CC work in 40% plum hard river boulder of 15 cm to 23 cm size and filled interstices with 60% cement concrete in proportion 1:3:6 with 13 mm to 38 mm size stone aggregate including curing, dewatering shuttering etc, complete as directed. (Shuttering cost will be paid separately)Cum7,409.62

Pricing pcc work with plum against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.