35 bridge items from the Assam Water Resources Department, effective 2023-04-01.
Bridge rates in the Assam Civil Works Schedule of Rates 2023-24 run from ₹51.25 to ₹1,90,128.27. Transcribed from Assam Water Resources (Irrigation) Department — Schedule of Rates (Civil Works) 2023-24. Reference only — verify against the official source before pricing a bid.
/
35 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 15.1 | Construction of 1.20 M wide bamboo foot bridge with 100 mm dia bhaluka / barak bamboo posts driven 120 cm to 180 cm under ground 3 nos. of each row being at 3 M apart tied with cane or wire bhaluka / barak bamboo dham placed over the posts and tied with the cane or wire bhaluka / barak bamboo strut in each row both upstream and downstream jati bamboo long girth closely placed and tied with dham single layers of mat placed over 75 mm thick brush wood and tied with bhaluka / barak bamboo rail stand fixed in one side of the bridge, complete as directed. SUPPLYING AND DRIVING PILES | Rm | 1,373.94 |
| 15.2 (A)(i) | Supplying and driving Sal piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH PILE ENGINEPortion of pile actually driven under ground | Rm | 7,705.07 |
| 15.2 (A)(ii) | Supplying and driving Sal piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH PILE ENGINEPortion of pile to remain above ground | Rm | 6,473.57 |
| 15.2 (B)(i) | Supplying and driving Sal piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH HAND SHAKINGPortion of pile actually driven under ground | Rm | 6,548.97 |
| 15.2 (B)(ii) | Supplying and driving Sal piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH HAND SHAKINGPortion of pile to remain above ground | Rm | 5,988.64 |
| 15.3 (A)(i) | Supplying and driving Azar / Nahar / Nageswar / Zamil piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH PILE ENGINEPortion of pile actually driven under ground | Rm | 6,648.83 |
| 15.3 (A)(ii) | Supplying and driving Azar / Nahar / Nageswar / Zamil piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH PILE ENGINEPortion of pile to remain above ground | Rm | 5,417.33 |
| 15.3 (B)(i) | Supplying and driving Azar / Nahar / Nageswar / Zamil piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH HAND SHAKINGPortion of pile actually driven under ground | Rm | 5,517.06 |
| 15.3 (B)(ii) | Supplying and driving Azar / Nahar / Nageswar / Zamil piles 25 cm to 30 cm dia dressed to hard wood including marking length in every 30 cm interval and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) — WITH HAND SHAKINGPortion of pile to remain above ground. WOODEN BRIDGE | Rm | 4,956.73 |
| 15.4 | Sal wood work including supplying fitting and fixing complete with necessary MS nuts bolts, screws etc. and coaltaring 2 coats with best tar applied hot (rate is inclusive of required quantity of the tar). Undressed in floor planks collars, bracing standard wheel guard struts and railing, tracking planks (alternate railing to be done with checking in stage and wing), runner belts, rail post | Cum | 1,90,128.27 |
| 15.5 | Supplying fitting and fixing sal timber beam and bearing beam rectangular in size fitted with MS cleats straps including supplying spikes etc. as necessary and coaltaring 2 coats with best tar applied hot. (Rate is inclusive of required quantity of the tar) | Cum | 1,18,439.73 |
| 15.6 | Supplying fitting 25 cm to 30 cm dia Sal wood long beam dressed to hardwood including supplying & fixing with 20 mm dia MS bolts and nuts including coaltaring 2 coats with best tar, applied hot as directed. (Rate is inclusive of cost of coaltar) | Rm | 4,706.03 |
| 15.7 | Azar / Nahar / Nageswar / Zarul / Cham / Sundi / Gumi woodwork including supplying, fitting and fixing complete with necessary nut-bolts, nails, screws etc. and coaltaring 2 coats with coal tar applied hot as directed. (Rate is inclusive of required quantity of the tar). Undressed in floor planks collars, bracing standard wheel guard struts and railing, runner belts, rail post, tracking planks | Cum | 74,359.65 |
| 15.8 | Supplying fitting and fixing Azar / Nahar / Nageswar / Zarul sawn timber beam and bearing beam rectangular in size fitted with MS cleats, straps including spikes etc. as necessary and coaltaring 2 coats with best tar applied hot as directed. (Rate is inclusive of required quantity of | Cum | 86,674.42 |
| 15.9 | Supplying fitting 25 cm to 30 cm dia Azar / Nahar / Nageswar / Zarul wood long beam dressed to hard wood including supplying & fixing with 20 mm dia MS bolts and nuts including coaltaring 2 coats with best tar, applied hot as directed | Rm | 6,656.92 |
| 15.10 | Supplying fitting and fixing RCC guard post of size 15 cm x 15 cm and 150 cm long of which 75 cm below ground including square base of size 45 cm x 45 cm x 15 cm with 4 nos. of 12 mm dia TS as main reinforcement and 6 mm dia stirrups at 30 cm c/c apart tying in position with black wire with cement concrete in proportion 1:2:4 with broken stone aggregate of size 6 mm to 20 mm including centering, shuttering and curing with 6 mm thick cement plastering in proportion 1:3 painted black & white alternatively in 23 cm stripe upto 75 cm from top keeping necessary goods etc. as per design and direction, complete as directed | Post | 2,064.29 |
| 15.11 | Supplying fitting and fixing 20 cm to 25 cm dia jungle wood dressed guard post 150 cm long 75 cm above ground and 72 cm to be driven under ground fitted with a horizontal struts size 0.05 M x 0.05 M x 0.55 M long at bottom with necessary nails including coaltaring 1 (one) coat the portion below ground and painting black & white 1 (one) coat alternately the portion above ground | Post | 2,700.22 |
| 15.12 | Screwing & joining of piles 25 cm to 30 cm dia dressed to hard wood 90 cm in length including supplying fitting and fixing with 2 nos. of 50 mm x 10 mm MS / FI clamps and 16 mm dia MS bolts and nuts etc, complete as directed | Joint | 2,553.16 |
| 15.13 | Labour for taking out old piles of the bridge and stacking them at suitable places as directed | Pile | 3,180.49 |
| 15.14 (A)(i) | Labour for driven piles 25 cm to 30 cm dia dressed to hard wood making length in every 30 cm including coaltaring with 2 coats with best tar applied hot including providing necessary scaffolding or staging as necessary. (Rate is inclusive of required quantity of tar) — With Pile EnginePortion of pile actually driven under ground | Rm | 2,513.07 |
| 15.14 (A)(ii) | Labour for driven piles 25 cm to 30 cm dia dressed to hard wood making length in every 30 cm including coaltaring with 2 coats with best tar applied hot including providing necessary scaffolding or staging as necessary. (Rate is inclusive of required quantity of tar) — With Pile EnginePortion of pile to remain above ground | Rm | 1,281.57 |
| 15.14 (B)(i) | Labour for driven piles 25 cm to 30 cm dia dressed to hard wood making length in every 30 cm including coaltaring with 2 coats with best tar applied hot including providing necessary scaffolding or staging as necessary. (Rate is inclusive of required quantity of tar) — With Hand ShakingPortion of pile actually driven under ground | Rm | 1,356.97 |
| 15.14 (B)(ii) | Labour for driven piles 25 cm to 30 cm dia dressed to hard wood making length in every 30 cm including coaltaring with 2 coats with best tar applied hot including providing necessary scaffolding or staging as necessary. (Rate is inclusive of required quantity of tar) — With Hand ShakingPortion of pile to remain above ground | Rm | 796.64 |
| 15.15 | Labour for fitting & fixing RS joist, beam, CI saddle in position including necessary scaffolding, cutting them to required size drilling holes and supply and fixing with necessary bolt, nuts, painting 2 coats, complete as directed. (Rate inclusive. of cost of tar and steel paint) | Rm | 1,235.88 |
| 15.16 | Labour for fitting & fixing old RS joist, beam & old CI saddle in position including necessary scaffolding and fixing with necessary cutting them to required size drilling holes and supplying and fixing with necessary bolts, nuts, painting 2 coats, complete as directed. (Rate inclusive of cost of tar and steel paint) | Rm | 1,061.67 |
| 15.17 | Labour for end fitting MS / FI straps of cleats etc. in position including drilling holes and carrying the same to site | Quintal | 5,419.25 |
| 15.18 | Labour charge for making 0.5 M x 0.50 M x 0.30 M size "U" shape MS flat iron strap from 150 mm x 12 mm size MS flat including providing 10 nos of holes and fitted with 0.35 M long 20 mm dia MS bolts including fitting lightly with bearing beam pits and RS beam etc, complete as directed. (Rate inclusive of the cost of MS bolts and nuts required) | Nos | 861.64 |
| 15.19 | Labour for fitting and fixing wood work including supplying and fixing with new bolts, nuts and spikes and coaltaring the coats applied hot. (Rate inclusive the cost of coaltar) | Rm | 5,100.10 |
| 15.20 | Labour for refitting wood work including sizing supplying and fixing necessary MS bolts, nuts and spikes and coaltaring 1 (one) coat applied hot as directed. (Rate inclusive the cost of coaltar) | Rm | 4,690.13 |
| 15.21 | Labour for fitting & fixing 25 cm to 30 cm dia long beam including supplying and fixing necessary MS bolts, nuts etc. and coaltaring the 2 coats, complete as directed. (Rate inclusive the cost of coaltar) | Rm | 817.22 |
| 15.22 | Labour for refitting & refixing 25 cm to 30 cm dia long beam including supplying and fixing necessary MS bolts, nuts etc. and coaltaring 1(one) coat applied as directed. (Rate inclusive the cost of coaltar) | Rm | 901.01 |
| 15.23 | Labour for taking out work of the bridge and refitting the same including supplying and fixing with necessary new MS bolts, nuts and spikes and nails etc. and coaltaring the 1 (one) coat applied hot as directed. (Rate inclusive. the cost of coaltar) | Sqm | 5,714.83 |
| 15.24 (A) | PAINTING WORKS IN BRIDGEClearing and painting work with the white paint: 1 (one) coat | Sqm | 93.93 |
| 15.24 (B) | PAINTING WORKS IN BRIDGEClearing and coaltaring wood works: 1 (one) coat | Sqm | 51.25 |
| 15.24 (C) | PAINTING WORKS IN BRIDGEClearing and painting iron works with aluminium paint - 1 (one) coat | Sqm | 115.99 |
Other chapters in this schedule
Pricing bridge against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.