Skip to main content
R/ASSAM SOR 2023-24

CC Work rates

36 cc work items from the Assam Water Resources Department, effective 2023-04-01.
Items
36
Lowest rate
₹7,366.10
Highest rate
₹10,901.43
Effective from
2023-04-01
S-01/RATE ITEMS36 ITEMS

CC Work rates in the Assam Civil Works Schedule of Rates 2023-24 run from ₹7,366.10 to ₹10,901.43. Transcribed from Assam Water Resources (Irrigation) Department — Schedule of Rates (Civil Works) 2023-24. For reference only: verify against the official source before pricing a bid.

Download the full schedule (Excel)All 22 chapters

36 items. Scroll the table to browse

DescriptionUnit
10.1 (A)(i)IN PROPORTION 1:1½:3 (M20) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:1½:3 with hard broken river stone aggregate of size 6 mm to 20 mm including curing, with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,517.78
10.1 (A)(ii)IN PROPORTION 1:1½:3 (M20) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:1½:3 with hard broken River stone aggregate of size 6 mm to 20 mm including curing, bailing out water with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,797.95
10.1 (A)(iii)IN PROPORTION 1:1½:3 (M20) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:1½:3 with hard broken river stone aggregate from river boulder of size 6 mm to 20 mm including curing, dewatering with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately). WITH HARD RIVER SHINGLES 6 MM TO 20 MMCum10,901.43
10.1 (B)(i)IN PROPORTION 1:1½:3 (M20)CC work in proportion 1:1½:3 with hard river shingles of size 6 mm to 20 mm including curing with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,995.07
10.1 (B)(ii)IN PROPORTION 1:1½:3 (M20)CC work in proportion 1:1½:3 with hard river shingles of size 6 mm to 20 mm including curing, bailing out water with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,275.24
10.1 (B)(iii)IN PROPORTION 1:1½:3 (M20)CC work in proportion 1:1½:3 with hard river shingles of size 6 mm to 20 mm including curing, dewatering with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,378.72
10.2 (A)(i)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 6 mm to 20 mm including curing with necessary timber shuttering, scaffolding where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,493.53
10.2 (A)(ii)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 6 mm to 20 mm including curing, bailing out water with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,773.70
10.2 (A)(iii)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 6 MM TO 20CC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 6 mm to 20 mm including curing, dewatering with necessary timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,877.18
10.2 (B)(i)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 6 MM TO 20 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 6 mm to 20 mm including curing with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,725.57
10.2 (B)(ii)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 6 MM TO 20 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 6 mm to 20 mm including curing, bailing out water with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,005.74
10.2 (B)(iii)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 6 MM TO 20 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 6 mm to 20 mm including curing, dewatering with necessary timber shuttering, scaffolding where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,109.22
10.2 (C)(i)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 13 TO 38 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,133.31
10.2 (C)(ii)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 13 TO 38 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing with bailing out water with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,413.48
10.2 (C)(iii)IN PROPORTION 1:2:4 (M15) — WITH HARD BROKEN STONE AGGREGATE 13 TO 38 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing including dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum10,516.96
10.2 (D)(i)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,497.11
10.2 (D)(ii)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:2:4 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing, bailing out water with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,777.28
10.2 (D)(iii)IN PROPORTION 1:2:4 (M15) — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:2:4 in foundation / abutment/ piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing with dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,880.76
10.3 (A)(i)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc.with hard broken stone aggregate of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,346.64
10.3 (A)(ii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing, bailing out water with necessary timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,626.81
10.3 (A)(iii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc.with hard broken stone aggregate of size 13 mm to 38 mm including curing, dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,730.29
10.3 (B)(i)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum7,866.19
10.3 (B)(ii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing, bailing out water with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,146.35
10.3 (B)(iii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 38 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing, dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,249.83
10.3 (C)(i)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 25CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with broken stone aggregate of size 13 mm to 25 mm including curing with timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,545.39
10.3 (C)(ii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 25CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 25 mm including curing, bailing out wate r with timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,825.56
10.3 (C)(iii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 25CC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 25 mm including curing, dewatering with timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,929.04
10.3 (D)(i)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 25 mm including curing with timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum7,976.98
10.3 (D)(ii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 25 mm including curing, bailing out water with timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,257.15
10.3 (D)(iii)IN PROPORTION 1:3:6 (M10) WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38 — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:3:6 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 25 mm including curing, dewatering with timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,360.63
10.4 (A)(i)IN PROPORTION 1:4:8 (M5) — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:4:8 in foundation / abutment / piers / wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum8,933.80
10.4 (A)(ii)IN PROPORTION 1:4:8 (M5) — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:4:8 in foundation / abutment / piers / wing walls etc.with hard broken stone aggregate of size 13 mm to 38 mm including curing, bailing out water with necessary timber shuttering, scaffolding etc. where necessary complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,213.96
10.4 (A)(iii)IN PROPORTION 1:4:8 (M5) — WITH HARD BROKEN STONE AGGREGATE 13 MM TO 38CC work in proportion 1:4:8 in foundation/ abutment/ piers/ wing walls etc. with hard broken stone aggregate of size 13 mm to 38 mm including curing and dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum9,317.44
10.4 (B)(i)IN PROPORTION 1:4:8 (M5) — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:4:8 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum7,366.10
10.4 (B)(ii)IN PROPORTION 1:4:8 (M5) — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:4:8 in foundation / abutment / piers / wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing, bailing out of water with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum7,646.26
10.4 (B)(iii)IN PROPORTION 1:4:8 (M5) — WITH HARD RIVER SHINGLES 13 MM TO 25 MMCC work in proportion 1:4:8 in foundation/ abutment/ piers/ wing walls etc. with hard river shingles of size 13 mm to 38 mm including curing, dewatering with necessary timber shuttering, scaffolding etc. where necessary, complete as directed. (Shuttering, scaffolding cost will be paid separately)Cum7,749.74
S-02/SOURCE RECORD2023-24
ISSUED BY
Assam Water Resources Department
EFFECTIVE
2023-04-01Financial year start. The schedule states only that it is for the year 2023-24 and effective from the date of publication; it prints no commencement date.
RETRIEVED
2026-07-29
S-03/CHAPTERS14 MORE

Other chapters in this schedule

SHOW ALL 14 CHAPTERS
ARCHED / ESTIMATING

Pricing cc work against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.