S-01/RATE ITEMS12 ITEMS
Steel Works rates in the Mizoram Schedule of Rates (Volume I) 2019 run from ₹86.40 to ₹921.50. Transcribed from Mizoram PWD — Schedule of Rates 2019 (Volume I), effective 1 February 2019; rates are inclusive of GST for a 5 km lead within Aizawl. For reference only: verify against the official source before pricing a bid.
/
Unit
12 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 10.02 | Providing and fixing ball bearing for rolling shutters | Nos | 300.10 |
| 10.03(a) | Extra for providing mechanical device, chain and crank operation for operating rolling shuttersExceeding 10.00 sqm and upto 16.80 sqm in area. (average say 14.00 sqm) | Sqm | 722.20 |
| 10.03(b) | Extra for providing mechanical device, chain and crank operation for operating rolling shuttersExceeding 16.80 sqm in area | Sqm | 921.50 |
| 10.07 | Structural steel work rivetted, bolted welded in built up sections, trusses and framed works, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. (In Tees, R.S. Joists, Angles, Flats and Channels.) | KG | 215.10 |
| 10.08 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.)trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete | KG | 176.40 |
| 10.10(a) | Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer. (round, square or rectangular hollow tubes etc.)MS tube 40mm @ 3.6 Kg/m | KG | 178.20 |
| 10.10(a) | Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer. (round, square or rectangular hollow tubes etc.)GI tube 40mm @ 3.72 Kg/m | KG | 189.70 |
| 10.12 | Providing and fixing a pair of flat iron brackets in concrete work while laying for jointing with timber post etc. including cost of bolts and nuts complete | Pair | 164.40 |
| 10.13 | Providing and fixing M.S. round or square bars without M.S flats at required spacings in wooden frame of windows and clerestory windows | KG | 90.60 |
| 10.14 | Providing and fixing M.S. round or square bars with M.S flats at required spacings in wooden frame of windows and clerestory windows | KG | 86.40 |
| 10.16(a) | Steel work welded in built up sections/framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as requiredIn stringers, treads, landings etc. of stair-cases including use of chequered plates wherever required all complete | KG | 159.90 |
| 10.17 | Structural steel work in single section fixed with or without connecting plate including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete | KG | 122.80 |
S-02/SOURCE RECORD2019
- ISSUED BY
- Mizoram PWD
- EFFECTIVE
- 2019-02-01
- RETRIEVED
- 2026-07-29
S-03/CHAPTERS21 MORE
Other chapters in this schedule
ARCHED / ESTIMATING
Pricing steel works against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.