Flooring rates in the Mizoram Schedule of Rates (Volume I) 2019 run from ₹19.80 to ₹524.60. Transcribed from Mizoram PWD — Schedule of Rates 2019 (Volume I), effective 1 February 2019; rates are inclusive of GST for a 5 km lead within Aizawl. Reference only — verify against the official source before pricing a bid.
/
15 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 12.01 | Cement concrete flooring 1:2:4 (1 cement: 2 sand: 4 well graded stone aggregate 20mm size) finished with a floating coat neat cement including cement slurry etc. complete but excluding the cost of nosing of steps etc. 40 mm thick with 20 mm nominal size stone aggregate | Sqm | 524.60 |
| 12.04 | Extra for making chequers of approved pattern on cement concrete floors, steps, landings, pavements, etc | Sqm | 50.60 |
| 12.05 | Cement plaster skirting or dado (upto 30cm height) with cement mortar 1:3 (1 cement: 3 sand) finished with a floating coat of neat cement including rounding of junction with floor | Sqm | 466.70 |
| 12.07(a) | Red oxide plaster skirting (upto 30cm height) with top layer of 6mm thick plaster of cement mortar red oxide mix using 3.5 kg of red oxide of iron per 50 kg of cement in mortar 1:3 (1 cement: 3 sand) finished with a floating coat of cement red oxide mix of the same proportion18mm thick with under layer 12mm thick cement plaster 1: 3 (1cement: 3sand) | Sqm | 497.40 |
| 12.07(b) | Red oxide plaster skirting (upto 30cm height) with top layer of 6mm thick plaster of cement mortar red oxide mix using 3.5 kg of red oxide of iron per 50 kg of cement in mortar 1:3 (1 cement: 3 sand) finished with a floating coat of cement red oxide mix of the same proportion21mm thick with under layer 15mm thick cement plaster 1: 3 (1cement: 3sand) | Sqm | 520.90 |
| 12.08 | Providing and fixing glass strips 40mm wide and 4mm thick in joints of terrazo / cement concrete floors | Rmt | 70.90 |
| 12.10 | Extra if chequered precast cement concrete tiles laid in treads of steps not exceeding 30cm in width | Sqm | 51.90 |
| 12.16 | Deduct for not grouting the joints with white cement and matching pigment in the items of fiwing of vitrified tiles | Sqm | 45.90 |
| 12.17 | Grouting the jounts of flooring tiles having joints of 3 mm width using epoxy grout mix of 0.70 kg of organic coated filler of desired shade(0.10kg of hardener and 0.20 kg of resin per kg) grouting and finishing complete as per direction of Engineer-in-charge | Sqm | 379.60 |
| 12.26 | Extra for pre finished nosing to treads of steps of marble stone | Sqm | 423.00 |
| 12.27 | Extra for marble stone flooring in treads lf steps and risers using single length upto 2.00m | Sqm | 446.40 |
| 12.31 | Extra for kota stone flooring in treads of steps and risers using single length upto 1.05m | Sqm | 19.80 |
| 12.32 | Extra for pre finished nosing in steps and treads of kota stone | Sqm | 139.40 |
| 12.37 | Extra for brick flooring laid in diagonal Herring Bond bond or other patterns | Sqm | 32.40 |
| 12.40 | Single layer rua bamboo turja flooring laid over split bamboo (phakrak) spaced 30cm apart over base frame of whole bamboo 50mm average dia. placed 30cm c/c complete including cost of base frame | Sqm | 358.70 |
Other chapters in this schedule
- Preparatory Works - Jungle Clearance (8)
- Earthwork (35)
- Plain Cement Concrete (5)
- Reinforced Cement Concrete (13)
- Brickworks (8)
- Marble and Granite Works (9)
- Wood & PVC Works (33)
- Steel Works (12)
- Aluminium Works (28)
- Walling (11)
- Doors & Windows Fittings (106)
- Ceiling (25)
- Roofing (19)
- Sanitary Installations (25)
- Water Supply (112)
- Water Proofing (19)
- Finishing (61)
- Horticulture & Landscaping (14)
- Fencing (5)
- Repairs to Buildings (92)
- Dismantling & Demolishing (40)
Pricing flooring against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works