8 preparatory works - jungle clearance items from the Mizoram PWD, effective 2019-02-01.
Items
8
Lowest rate
₹3.00
Highest rate
₹252.90
Effective from
2019-02-01
S-01/RATE ITEMS8 ITEMS

Preparatory Works - Jungle Clearance rates in the Mizoram Schedule of Rates (Volume I) 2019 run from ₹3.00 to ₹252.90. Transcribed from Mizoram PWD — Schedule of Rates 2019 (Volume I), effective 1 February 2019; rates are inclusive of GST for a 5 km lead within Aizawl. For reference only: verify against the official source before pricing a bid.

Download the full schedule (Excel)All 24 chapters
Unit

8 items. Scroll the table to browse

DescriptionUnit
1.01Clearing grass and removal of rubbish upto a distance of 50 metres outside the periphery of the area cleared. By Manual meansSqm6.80
1.02(a)(i)Clearing and grubbing road land including uprooting rank vegetation, grass, brush shrubs, saplings and trees of girth upto 300 mm, removal of stumps, disposal of unserviceable material and stacking of serviceable material upto 100 metres from road boundary — By manual meansIn area of light jungleSqm9.10
1.02(a)(ii)Clearing and grubbing road land including uprooting rank vegetation, grass, brush shrubs, saplings and trees of girth upto 300 mm, removal of stumps, disposal of unserviceable material and stacking of serviceable material upto 100 metres from road boundary — By manual meansIn area of thorny jungleSqm13.60
1.02(b)Clearing and grubbing road land including uprooting rank vegetation, grass, brush shrubs, saplings and trees of girth upto 300 mm, removal of stumps, disposal of unserviceable material and stacking of serviceable material upto 100 metres from road boundaryBy Mechanical means. (for all classes of jungle)Sqm3.00
1.03(a)(i)Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30cm measured at a height of 1m above ground level and removal of rubbish upto a distance of 50 metres outside the periphery of the area cleared — By manual meansLight jungleSqm7.00
1.03(a)(ii)Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30cm measured at a height of 1m above ground level and removal of rubbish upto a distance of 50 metres outside the periphery of the area cleared — By manual meansMedium jungleSqm10.60
1.03(a)(iii)Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30cm measured at a height of 1m above ground level and removal of rubbish upto a distance of 50 metres outside the periphery of the area cleared — By manual meansHeavy jungleSqm14.10
1.04(a)Felling trees of girth (measured at a height of 1m above ground level) including cutting of trunks and branches and removing the roots and stacking of serviceable material and disposal of unserviceable material with all lifts and upto a lead of 100 metres and earth filling in the depression/pitG irth from 30 cm to 60 cmNos252.90
S-02/SOURCE RECORD2019
ISSUED BY
Mizoram PWD
EFFECTIVE
2019-02-01
RETRIEVED
2026-07-29
S-03/CHAPTERS21 MORE

Other chapters in this schedule

SHOW ALL 21 CHAPTERS
ARCHED / ESTIMATING

Pricing preparatory works - jungle clearance against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.