Mizoram SOR 2019
Fencing rates
5 fencing items from the Mizoram PWD, effective 2019-02-01.
Fencing rates in the Mizoram Schedule of Rates (Volume I) 2019 run from ₹104.20 to ₹964.40. Transcribed from Mizoram PWD — Schedule of Rates 2019 (Volume I), effective 1 February 2019; rates are inclusive of GST for a 5 km lead within Aizawl. Reference only — verify against the official source before pricing a bid.
/
5 items — scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 22.04(a) | 1.0m high plastic net fencing with 1.5m angle iron posts 40 x 40 x 6mm size placed at 2.5m apart embedded in cement concrete block 1:3:6 (1 cement: 3 sand: 6 stone aggegate) of size 25 x 25 x 60 cm with necessary fittings including earthwork completePerimeter fencing 2MW | Rmt | 964.40 |
| 22.04(b) | 1.0m high plastic net fencing with 1.5m angle iron posts 40 x 40 x 6mm size placed at 2.5m apart embedded in cement concrete block 1:3:6 (1 cement: 3 sand: 6 stone aggegate) of size 25 x 25 x 60 cm with necessary fittings including earthwork completeSGP - 16 41" MW | Rmt | 757.80 |
| 22.05(a) | 1.2m high steel wire fabric fencing with 1.8m angle iron posts 40 x 40 x 6mm size placed at 2.0m apart embedded in cement concrete block 1:3:6 (1 cement: 3 sand: 6 stone aggegate) of size 25 x 25 x 60 cm with necessary fittings including earthwork completeExpanded wire mesh 3" | Rmt | 796.30 |
| 22.06 | Bamboo fencing 1.00m high using seasoned bamboos of 30 mm average diameter quartered and smoothened, in Zawngdaikhalh pattern with specified spacing and strengthened (covered) with two semi-circular sections both at the top and bottom with balli posts at 2 metres intervals and binding with wires including earthwork complete | Rmt | 118.20 |
| 22.09 | Extra for applying two coats of synthetic enamel paints over one coat of red oxide zinc primer on angle iron posts and struts, complete in all respects as per drawing and direction of Engineer-in-charge | Rmt | 104.20 |
Other chapters in this schedule
- Preparatory Works - Jungle Clearance (8)
- Earthwork (35)
- Plain Cement Concrete (5)
- Reinforced Cement Concrete (13)
- Brickworks (8)
- Marble and Granite Works (9)
- Wood & PVC Works (33)
- Steel Works (12)
- Aluminium Works (28)
- Flooring (15)
- Walling (11)
- Doors & Windows Fittings (106)
- Ceiling (25)
- Roofing (19)
- Sanitary Installations (25)
- Water Supply (112)
- Water Proofing (19)
- Finishing (61)
- Horticulture & Landscaping (14)
- Repairs to Buildings (92)
- Dismantling & Demolishing (40)
Pricing fencing against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.