Pile Driving rates
- Items
- 9
- Lowest rate
- ₹2.97
- Highest rate
- ₹99.05
- Effective from
- 2023-04-20
Pile Driving rates in the Odisha Schedule of Rates — Miscellaneous Items (Chapter 25) 2022 run from ₹2.97 to ₹99.05. Transcribed from Government of Odisha, Works Department — Schedule of Rates 2022, Chapter 25 (Miscellaneous Items) only. Chapters 5–24 of this document — earthwork, concrete, RCC, masonry, flooring, painting, roofing, road work, bridge works and the other core trades — carry no rates; each directs the reader to the Analysis of Rates, 2006. Chapters 1–4 are basic rates of materials, labour, conveyance and machinery, not items of work.. For reference only: verify against the official source before pricing a bid.
9 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 25.9.1 | Labour for driving sal bullah piles and fixing in position 12cm to 15cm, dia upto 1.50M depth including sharpening the end | Metre | 16.65 |
| 25.9.3 | Ditto-Ditto above 15 Cm and upto 20cm dia upto 1.50M depth | Metre | 28.69 |
| 25.9.5 | Ditto-Ditto above 20 Cm and upto 20cm dia upto 1.50M depth | Metre | 37.86 |
| 25.9.7 | Ditto-Ditto above 25 Cm and upto 20cm dia upto 1.50M depth | Metre | 43.04 |
| 25.9.10 | Bamboo piling 1.50M long 30cm apart to be driven to a depth of 90Cm with 60Cm jafree on top | Rm | 34.45 |
| 25.9.11 | Bamboo piling 2.00M long 30cm apart to be driven to a depth of 1.0M with 90Cm jafree on top | Rm | 42.21 |
| 25.9.12 | Bamboo piling 3.7M long 30cm apart to be driven to a depth of 2M with 1.50M jafree on top | Rm | 99.05 |
| 25.9.13 | Half bullah tying pieces fitted and fixed with nails (labour only) | Rm | 9.01 |
| 25.9.14 | For driving piles in water add extra to the respective rate of pile driving item | Rm | 2.97 |
- ISSUED BY
- Odisha Works Department
- EFFECTIVE
- 2023-04-20Date of the covering Office Memorandum, which the text layer does not carry — it is an image page, read visually. OM No. WORKS-FA-MISCSB-0015-2022 6785/W dated 20-4-2023 states: "The new Schedule of Rate-2022 are effective from the date of issue of this Office Memorandum."
- RETRIEVED
- 2026-07-29
Other chapters in this schedule
Pricing pile driving against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.