Painting rates
- Items
- 9
- Lowest rate
- ₹2.01
- Highest rate
- ₹9.19
- Effective from
- 2023-04-20
Painting rates in the Odisha Schedule of Rates — Miscellaneous Items (Chapter 25) 2022 run from ₹2.01 to ₹9.19. Transcribed from Government of Odisha, Works Department — Schedule of Rates 2022, Chapter 25 (Miscellaneous Items) only. Chapters 5–24 of this document — earthwork, concrete, RCC, masonry, flooring, painting, roofing, road work, bridge works and the other core trades — carry no rates; each directs the reader to the Analysis of Rates, 2006. Chapters 1–4 are basic rates of materials, labour, conveyance and machinery, not items of work.. For reference only: verify against the official source before pricing a bid.
9 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 25.8.1 | Painting figures and letters of various size upto 120mm | Each | 2.04 |
| 25.8.2 | Painting figures and letters above 120 mm size | Rm | 2.01 |
| 25.8.3 | Engraving letters of various sizes from 5cm to 10cm including painting, etc. Complete | Rm | 3.41 |
| 25.8.4 | Painting and writing road signs of all kinds as per I.R.C. standard including painting boards | Rm | 9.19 |
| 25.8.5 | Marking and painting lines or arrows | Rm | 2.79 |
| 25.8.6 | Wall painting with any approved paint 1 coat (Labour only) | Sqm | 5.75 |
| 25.8.7 | Wall painting with any approved paint 2 coats (Labour only) | Sqm | 6.93 |
| 25.8.8 | Scraping old paint with scrapers, sand papering andwashing with soap water or soda including scaffolding charges upto 5M height | Sqm | 5.12 |
| 25.8.9 | Scraping old paint with scrapers, sand papering and washing with soap water or soda including scaffolding charges above 5M high and upto 8M height | Sqm | 7.01 |
- ISSUED BY
- Odisha Works Department
- EFFECTIVE
- 2023-04-20Date of the covering Office Memorandum, which the text layer does not carry — it is an image page, read visually. OM No. WORKS-FA-MISCSB-0015-2022 6785/W dated 20-4-2023 states: "The new Schedule of Rate-2022 are effective from the date of issue of this Office Memorandum."
- RETRIEVED
- 2026-07-29
Other chapters in this schedule
Pricing painting against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.