R/HARYANA SOR 2021
Bridges (Substructure, Superstructure, Bearings & Expansion Joints) rates
32 bridges (substructure, superstructure, bearings & expansion joints) items from the Haryana PWD (Buildings & Roads), effective 2021-03-31.
- Items
- 32
- Lowest rate
- ₹69.00
- Highest rate
- ₹68,876.00
- Effective from
- 2021-03-31
S-01/RATE ITEMS32 ITEMS
Bridges (Substructure, Superstructure, Bearings & Expansion Joints) rates in the Haryana Haryana Schedule of Rates 2021 run from ₹69.00 to ₹68,876.00. Transcribed from Haryana PWD (B&R) — Haryana Schedule of Rates 2021, issued with the approval of the Direction Committee of Chief Engineers, 31 March 2021. For reference only: verify against the official source before pricing a bid.
/
Unit
32 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 27.1 | Brick masonry work in 1:3 in sub-structure including scaffolding complete excluding pointing and plastering, as per drawing and MoRT&H Specifications 1300 and 2200 | Cum | 5,467.00 |
| 27.2 | Pointing with cement mortar (1:3) on brick work in substructure as per MoRT&H Specifications Scaffolding is already included in item 27.1 | Sqm | 69.00 |
| 27.3 | Plastering (12 mm thick) with cement mortar (1:3 ) on brick work in sub-structure as per MoRT&H Specifications 1.Scaffolding is already included in item no. 27.1 2.The number of masons and Mazdoors already catered in the cement mortar have been taken into account while providing these categories in brick masonry, pointing and plastering | Sqm | 121.00 |
| 27.4.1 | Stone masonry work in cement mortar 1:3 for substructure including scaffolding complete as per drawing and MoRT&H MORT&H Specifications 1400 and 2200Random Rubble Masonry ( coursed/uncoursed) | Cum | 4,941.00 |
| 27.4.2 | Stone masonry work in cement mortar 1:3 for substructure including scaffolding complete as per drawing and MoRT&H MORT&H Specifications 1400 and 2200Coursed rubble masonry (first sort) | Cum | 5,291.00 |
| 27.4.3 | Stone masonry work in cement mortar 1:3 for substructure including scaffolding complete as per drawing and MoRT&H MORT&H Specifications 1400 and 2200Ashlar masonry ( first sort ) Plain ashlar The labour already considered in the cement mortar have been taken into account while providing these categories in the stone masonry works. PlainlReinforced cement concrete in sub- structure complete as per drawing and MORT&H MoRT&H Specifications 1500,1700 and 2200 | Cum | 6,604.00 |
| 27.5 | PCC Grade M15 (with concrete Mixer) Height up to 5m | Cum | 4,462.00 |
| 27.6 | PCC Grade M20 (with concrete Mixer) Height up to 5m | Cum | 5,068.00 |
| 27.7.1 | Height up to 5m 27. 7. 1.1 Using concrete Mixer | Cum | 5,456.00 |
| 27.7.2 | Height 5m to 10m 27. 7.2.1 Using concrete Mixer 27.7. 2.2 With Batching Plant, Transit Mixer and Concrete Pump | Cum | 5,555.00 |
| 27.7.3 | Height above 1O m 27. 7.3.1 Using concrete Mixer | Cum | 5,903.00 |
| 27.13 | Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and MoRT&H Specifications | Tonne | 68,876.00 |
| 27.14 | Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and MoRT&H Specification | Tonne | 67,302.00 |
| 27.15 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ retum wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V:20H towards drawing force. Complete as per drawing and MoRT&H Specifications | Nos | 258.00 |
| 27.16.1 | Back tilling behind abutment, wing wall and return wall complete as per drawing and MoRT&H SpecificationGranular material | Cum | 1,411.00 |
| 27.25 | RCC Grade M20, Using Concrete Mixer | Cum | 4,590.00 |
| 27.25.1.1 | For solid slab super-structure, Add 20-30 per cent of labour, material and machinery cost for FormworkHeight up to 5m | Cum | 5,508.00 |
| 27.25.1.2 | For solid slab super-structure, Add 20-30 per cent of labour, material and machinery cost for FormworkHeight 5m to 10m | Cum | 5,738.00 |
| 27.25.1.3 | For solid slab super-structure, Add 20-30 per cent of labour, material and machinery cost for FormworkHeight above 1 Om | Cum | 5,967.00 |
| 27.26 | RCC M-20, Using Batching Plant, Transit Mixer and Concrete Pump | Cum | 3,949.00 |
| 27.26.1.2 | For solid slab super-etructure, 20-30 per cent of labour, material and machinery costHeight 5m to 1O m | Cum | 4,936.00 |
| 27.27 | RCC Grade M25 Using Concrete Mixer For formwork and staging add the following | Cum | 4,960.00 |
| 27.27.1.3 | For solid slab super-structure, 20-30 per cent of labour, material and machinery costHeight above 1 Om | Cum | 6,448.00 |
| 27.28 | Using Batching Plant, Transit Mixer and Concrete Pump For formwork and staging add the following | Cum | 4,324.00 |
| 27.28.1.3 | For solid slab super-structure, 20-30 per cent of labour, material and machinery costHeight above 10m | Cum | 5,621.00 |
| 27.29 | RCC Grade M 30 Using Concrete Mixer | Cum | 5,040.00 |
| 27.29.1.1 | For solid slab supar-etructure, 20-30 par cant of labour, material and machinery costHeight up to 5m | Cum | 6,048.00 |
| 27.29.1.2 | For solid slab supar-etructure, 20-30 par cant of labour, material and machinery costHeight 5m to 10m | Cum | 6,299.00 |
| 27.29.1.3 | For solid slab supar-etructure, 20-30 par cant of labour, material and machinery costHeight above 1 Om | Cum | 6,551.00 |
| 27.29.2.2 | For T-beam & slab, 25-35 per cent of labour, material and machinery costHeight 5m to 1 Om | Cum | 6,551.00 |
| 27.30 | Using Batching Plant, Transit Mixer and Concrete Pump. For formwork and staging add the following | Cum | 4,376.00 |
| 27.30.1.2 | For solid slab super-etructure, 20-30 per cent of labour, material and machinery costHeight 5m to 10m | Cum | 5,470.00 |
S-02/SOURCE RECORD2021
- ISSUED BY
- Haryana PWD (Buildings & Roads)
- EFFECTIVE
- 2021-03-31HSR 2021 states no commencement date. This is the date the foreword records the schedule as issued, with the approval of the Direction Committee of Chief Engineers, and is inferred rather than transcribed.
- RETRIEVED
- 2026-07-29
S-03/CHAPTERS27 MORE
Other chapters in this schedule
- Earth Work and Rock Cutting71
- Dismantling and Demolition93
- Concrete and RCC Work148
- Brick Work and Stone Masonry101
- Cladding Work61
- Hoisting and Roofing126
- Flooring and Dados181
- Finishing Works129
- Wood Work, PVC and Aluminum Doors and Windows291
- Steel and Iron Work64
- Lining and Outlets71
- Deep Foundations141
SHOW ALL 27 CHAPTERS
- River and Canal Protection Works57
- Road Works112
- Miscellaneous (Buildings)114
- Water Supply879
- Sewerage and Drainage1019
- Sanitary Installations642
- Horticulture and Land Scaping125
- Water Proofing and Heat Insulation of Buildings54
- Structural & Aluminium Glazing7
- Repairs and Maintenance of Buildings146
- Strengthening and Retrofitting of Buildings34
- Innovating Technologies, New Materials and Solar Panels123
- Rain Water Harvesting & Tube wells45
- Road Furniture82
- Miscellaneous (Roads)35
ARCHED / ESTIMATING
Pricing bridges (substructure, superstructure, bearings & expansion joints) against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.