Skip to main content

Chhattisgarh SOR 2026

Horticulture & Landscaping rates

32 horticulture & landscaping items from the Chhattisgarh Public Works Department (PWD), effective 2026-06-10.

Horticulture & Landscaping rates in the Chhattisgarh Building Schedule of Rates 2026 run from ₹0.90 to ₹2,008.00. Transcribed from Chhattisgarh PWD — Modified Building SOR, 10 June 2026. Reference only — verify against the official source before pricing a bid.

32 items — scroll the table to browse

DescriptionUnit
22.1Trenching in ordinary soil upto a depth of 60cm including removal and stacking of serviceable materials and then disposing of by spreading and neatly leveling with in a lead of 50m and making up the trenched area to proper levels by filling with earth or earth mixed with sludge or/and manure before and after flooding trench with water (excluding cost of imported earth, sludge or manure)Cum98.00
22.2Supplying and stacking of good earth at site including royalty, loading, unloading and carriage upto 5 km (earth measured in stacks will be reduced by 20% for payment)Cum171.00
22.3Supplying and stacking sludge at site including royalty, loading, unloading and carriage upto 5 km (sludge measured in stacks will be reduced by 8% for payment)Cum211.00
22.4Supplying and stacking at site well decayed cow dung manure from approved source, including loading, unloading and carriage upto 5 km (manure measured in stacks will be reduced by 8% for payment)Cum201.00
22.6Uprooting weeds from the trenched area after 10 to 15 days of its flooding with water including disposal of uprooted vegetationSqm1.40
22.7Fine dressing the groundSqm0.90
22.8Spreading of sludge, dump manure or/and good earth in required thickness (Cost of sludge, dump manure or/ and good earth to be paid separately)Cum15.00
22.9Mixing earth and sludge or manure in proportion specified or directedCum9.40
22.10.1Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for mowing including supplying good earth if needed (the good earth shall be paid for separately).In rows 15 cm apart in either directionSqm2.30
22.10.2Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for mowing including supplying good earth if needed (the good earth shall be paid for separately).In rows 7.5 cm apart in either directionSqm3.20
22.10.3Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for mowing including supplying good earth if needed (the good earth shall be paid for separately).In rows 5 cm apart in either directionSqm5.60
22.11Renovating lawns including weeding, cheeling the grass, forking the ground, top dressing with sludge or manure, mixing the same with forked soil, watering and maintaining the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for mowing and disposal of rubbish as directed, including supplying good earth if needed but excluding the cost of sludge or manure (the good earth shall be paid for separately)Sqm9.00
22.12Uprooting rank vegetation and weeds by digging the area to a depth of 60cm removing all weeds and other growth with roots by forking repeatedly, breaking clods, rough dressing, flooding with water, uprooting fresh growths after 10 to 15 days and then fine dressing for planting new grass, including disposal of all rubbish with all leads and liftsSqm16.00
22.13Preparation of beds for hedging and shrubbery by excavating 60cm deep and trenching the excavated base to a further depth of 30cm, refilling the excavated earth after breaking clods and mixing with sludge or manure in the ratio of 8:1 (8 parts of stacked volume of earth after reduction by 20%: one part of stacked volume of sludge or manure after reduction by 8%), flooding with water, filling with earth if necessary, watering and finally fine dressing, leveling etc. including stacking and disposal of materials declared unserviceable and surplus earth by spreading and leveling as directed, within a lead of 50m lift upto 1.5 m complete (cost of sludge, manure or extra earth to be paid for separately)Cum98.00
22.14.1Digging holes in ordinary soil and refilling the same with the excavated earth mixed with manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after reduction by 20%: 1 part of stacked volume of manure after reduction by 8%) flooding with water, dressing including removal of rubbish and surplus earth, if any with all leads and lifts (cost of manure, sludge or extra good earth if needed to be paid for separately):Holes 1.2 m dia and 1.2 m deepEach233.00
22.14.2Digging holes in ordinary soil and refilling the same with the excavated earth mixed with manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after reduction by 20%: 1 part of stacked volume of manure after reduction by 8%) flooding with water, dressing including removal of rubbish and surplus earth, if any with all leads and lifts (cost of manure, sludge or extra good earth if needed to be paid for separately):Holes 60 cm dia, and 60 cm deepEach28.00
22.15Half brick circular tree guard in modular well burnt clay bricks of crushing strength not less than 25kg/ sqcm, internal diameter 1.25 metre and height 1.2 metre above ground and 0.20 m below ground bottom two courses laid dry and top three courses in cement mortar 1:6 (1 cement: 6 fine sand) and the intermediate courses being in dry honey comb masonry as per design completeEach1,055.00
22.16Providing and fixing M.S. flat iron tree guard 60cm dia. and 2m height above ground level formed of 4 nos. 25x6mm and 8 nos. 25x3mm vertical M.S. flats riveted to 3 nos. 25x6mm M.S. flat iron rings in two halves, bolted together with 8mm dia. and 30mm long bolts including painting two coats with paint of approved brand and manufacture over a coat of priming, complete in all respectsEach2,008.00
22.17.1Making tree guard 53 cm dia. and 1.3 m high as per design from empty coal tar drums supplied free by the department including providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects including painting inside and outside of tree guard with:A coat of coal tarEach352.00
22.17.2Making tree guard 53 cm dia. and 1.3 m high as per design from empty coal tar drums supplied free by the department including providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects including painting inside and outside of tree guard with:Two or more coats of synthetic enamel paint of approved quality shade over a priming coatEach433.00
22.18.1Making tree guard 53 cm dia. and 2 m high as per design from empty coal tar drums supplied free by the department including providing and fixing four legs 40 cm long of 30 x 3 mm M.S. flat riveted to tree guard and providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects including painting inside and outside of tree guard with:A coat of coal tarEach278.00
22.18.2Making tree guard 53 cm dia. and 2 m high as per design from empty coal tar drums supplied free by the department including providing and fixing four legs 40 cm long of 30 x 3 mm M.S. flat riveted to tree guard and providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects including painting inside and outside of tree guard with:Two or more coats of synthetic enamel paint of approved quality and shade over a priming coatEach402.00
22.19Edging with modular well burnt clay bricks of crushing strength not less than 25kg/ sqcm laid dry length wise including excavation, refilling, consolidating with hand packing and spreading neatly surplus earth within a lead of 50 mMetre24.00
22.20Filling mixture of earth and sludge or manure in the desired proportion in trenches, flooding with water and leveling (cost of supplying earth and sludge or manure and mixing excluded)Cum5.00
22.21Excavation in dumped stones or malba including stacking of serviceable and unserviceable material separately and disposal of unserviceable material lead upto 50 m and lift upto 1.5 m disposed material to be neatly dressedCum131.00
22.22Excavation in bajri path including stacking of serviceable and unserviceable material lead upto 50 m and lift upto 1.5 m disposed material to be neatly dressedCum150.00
22.23Excavation in water bound macadam road including stacking the serviceable and unserviceable material separately and disposal of unserviceable material lead upto 50 m and lift upto 1.5 m disposed material to be neatly dressedCum186.00
22.24Flooding the ground with water including making kiaries and dismantling the sameSqm0.90
22.25.1Providing and planting following herbs in garden including preparation of soil, base plantation, providing and spreading different fertilizers, soil and sand:Hedges like Alife, Dorenta, Tikoma etcEach12.00
22.25.2Providing and planting following herbs in garden including preparation of soil, base plantation, providing and spreading different fertilizers, soil and sand:Furn like Arica, China etc (3 year old)Each106.00
22.25.3Providing and planting following herbs in garden including preparation of soil, base plantation, providing and spreading different fertilizers, soil and sand:Hibiscus (Flower)/ RoseEach23.00
22.25.4Providing and planting following herbs in garden including preparation of soil, base plantation, providing and spreading different fertilizers, soil and sand:Carpet grass (well developed)Sqm224.00

Pricing horticulture & landscaping against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.