10 mortars items from the Tripura PWD (R&B and Buildings), effective 2023-04-01.

Mortars rates in the Tripura Building Schedule of Rates 2023 run from ₹895.60 to ₹8,451.70. Transcribed from Tripura PWD — SoR 2023: Building Works, basic rates as on or just before 01.04.2023. Reference only — verify against the official source before pricing a bid.

10 items — scroll the table to browse

DescriptionUnit
3.1.1Mortar 1: 1 (1 cement: 1 fine sand)Cum7,974.50
3.1.2Mortar 1: 2 (1 cement: 2 fine sand)Cum5,829.70
3.1.3Mortar 1: 3 (1 cement: 3 fine sand)Cum4,758.50
3.1.4Mortar 1: 4 (1 cement: 4 fine sand)Cum3,857.90
3.1.5Mortar 1: 5 (1 cement: 5 fine sand)Cum3,372.90
3.1.6Mortar 1: 6 (1 cement: 6 fine sand)Cum2,957.30
3.2.1Stone Dust Mortar 1: 2 (1 cement: 2 Stone dust)Cum7,634.70
3.3.1Marble Dust Mortar 1: 2 (1 cement: 2 Marble dust)Cum8,451.70
3.3.2Marble Dust Mortar 1: 5 (1 cement: 5 Marble dust)Cum6,326.10
3.5Mortar extra @ 5% for labour charges & hire charges, water sundries and contingencies in case of mechanical of mortar. Carriage of concrete by transit mixer. Hire charge of Concrete mixer 0.25-0.40 cubic metre with hopper Hire charge of Pump set of capacity 4000 litres/hour Production cost of concrete by batch mix plant. Pumping charges of concrete including Hire charges of pump, piping work & accessories etc. Hire charge of Vibrator (Needle type 40 mm) Bhisti/Waterman Beldar Coolie Foreman Mason (average) Carpenter (average) Brick Aggregate (Single size): 40 mm nominal size Brick Aggregate (Single size): 20 mm nominal size Brick Aggregate (Single size): 12 mm nominal size Stone Aggregate (Single size): 40 mm nominal size Stone Aggregate (Single size): 25 mm nominal size Stone Aggregate (Single size): 20 mm nominal size Stone Aggregate (Single size): 12 mm nominal size Stone Aggregate (Single size): 10 mm nominal size Stone Aggregate (Single size): 06 mm nominal size Local ballies 100/125 mm diameter Paving Bitumen (paving) grade VG-10 of approved quality Cement (Portland) Coal (steam) Kerosene oil Sand (Fine): Selected quarry Mild steel round bar above 12 mm dia Structural steel such as tees, angles channels and R.S. joists Flats up to 10 mm in thickness Mild steel sheets for tanks Galvanised steel bolts & nuts 10 mm dia and 125 mm long round head with slots Mild stel bolts 6 mm dia and 25 mm long with hexagonal head Straining bolts Second class local wood in scantling Second class local wood in planks Water proofing materials Double clip ( bridge clip) Single clip M.S. tube 40 mm dia M.S. tube 50 mm dia Column clamp 450x1070 m Synthetic polyester triangular fibre of length 12mm, effective dia 10-40 microns and specific gravity of 1.34 to 1.40 Plasticizer / super plasticizer Carriage: Steam coal Carriage: Brick/ Stone aggregate below 40 mm nominal size Carriage: Timber Carriage: Steel Carriage: Brick/ Stone aggregate 40 mm nominal size and above Carriage: Cement Carriage: Tar bitumen Carriage: Fine Sand 1. Sand can be either coarse or fine as required/available. Here, provision considered only due to non-availability of coarse sand in Tripura. However, dictates for use of coarse sand, then seperate analysis may be made 2. The quantities of Cement, sand and coarse aggregates are as per Book 3. Cement concrete with volumetric mix proportion cannot be termed grade, because as per IS Code, only the design mix grades of concrete grade M-15, concrete grade M-20 etc. Hence in this case it should be etc. for batching with specified proportion. 4. The calculations are based on the assumption that 20 cum. to 25 laid in a day. 5. The provision of waterman is mainly for feeding water for mixing requirements during concreting. 6. The expenses for curing will be covered by the provision of WaterCum895.60

Pricing mortars against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.