R/MADHYA PRADESH SOR 2023
Reinforced Cement Concrete Pipes rates
190 reinforced cement concrete pipes items from the Madhya Pradesh Public Health Engineering Department (PHED), effective 2023-09-01.
- Items
- 190
- Lowest rate
- ₹81.00
- Highest rate
- ₹19,522.00
- Effective from
- 2023-09-01
S-01/RATE ITEMS190 ITEMS
Reinforced Cement Concrete Pipes rates in the Madhya Pradesh Unified Schedule of Rates 2023 run from ₹81.00 to ₹19,522.00. Transcribed from Madhya Pradesh PHED — Unified Schedule of Rates for Water Supply, Sewerage and Allied Works, in force from 1 September 2023. For reference only: verify against the official source before pricing a bid.
/
190 items. Scroll the table to browse
| Description | Unit | ||
|---|---|---|---|
| 28.1.1 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints100 mm dia | Metre | 444.00 |
| 28.1.2 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints150 mm dia | Metre | 498.00 |
| 28.1.3 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints200 mm dia | Metre | 524.00 |
| 28.1.4 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints250 mm dia | Metre | 764.00 |
| 28.1.5 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints300 mm dia | Metre | 989.00 |
| 28.1.6 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints350 mm dia | Metre | 1,137.00 |
| 28.1.7 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints400 mm dia | Metre | 1,154.00 |
| 28.1.8 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints450 mm dia | Metre | 1,399.00 |
| 28.1.9 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints500 mm dia | Metre | 1,527.00 |
| 28.1.10 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints600 mm dia | Metre | 1,925.00 |
| 28.1.11 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints700 mm dia | Metre | 2,528.00 |
| 28.1.12 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints800 mm dia | Metre | 3,357.00 |
| 28.1.13 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints900 mm dia | Metre | 4,154.00 |
| 28.1.14 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1000 mm dia | Metre | 4,784.00 |
| 28.1.15 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1100 mm dia Rate SI NO. Particulars of Items Unit | Metre | 5,614.00 |
| 28.1.16 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1200 mm dia | Metre | 6,915.00 |
| 28.1.17 | Providing and laying non-pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1600 mm dia | Metre | 11,452.00 |
| 28.2.1 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints100 mm dia | Metre | 84.00 |
| 28.2.2 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints150 mm dia | Metre | 131.00 |
| 28.2.3 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints200 mm dia | Metre | 141.00 |
| 28.2.4 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints250 mm dia | Metre | 191.00 |
| 28.2.5 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints300 mm dia | Metre | 230.00 |
| 28.2.6 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints350 mm dia | Metre | 253.00 |
| 28.2.7 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints400 mm dia | Metre | 292.00 |
| 28.2.8 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints450 mm dia | Metre | 335.00 |
| 28.2.9 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints500 mm dia | Metre | 371.00 |
| 28.2.10 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints600 mm dia | Metre | 436.00 |
| 28.2.11 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints700 mm dia | Metre | 491.00 |
| 28.2.12 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints800 mm dia | Metre | 563.00 |
| 28.2.13 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints900 mm dia | Metre | 691.00 |
| 28.2.14 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1000 mm dia | Metre | 764.00 |
| 28.2.15 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1100 mm dia | Metre | 836.00 |
| 28.2.16 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1200 mm dia | Metre | 945.00 |
| 28.2.17 | Labour only for Laying and Jointing non pressure (NP2) RCC socket & spigot pipes with rubber gasket joint including testing of joints1600 mm dia | Metre | 1,363.00 |
| 28.3.1 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints150 mm dia | Metre | 642.00 |
| 28.3.2 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints250 mm dia | Metre | 907.00 |
| 28.3.3 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints300 mm dia | Metre | 1,123.00 |
| 28.3.4 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints350 mm dia | Metre | 1,798.00 |
| 28.3.5 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints400 mm dia | Metre | 2,175.00 |
| 28.3.6 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints450 mm dia | Metre | 2,512.00 |
| 28.3.7 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints500 mm dia | Metre | 2,760.00 |
| 28.3.8 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints600 mm dia | Metre | 3,297.00 |
| 28.3.9 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints700 mm dia | Metre | 4,431.00 |
| 28.3.10 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints800 mm dia | Metre | 5,793.00 |
| 28.3.11 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints900 mm dia | Metre | 7,118.00 |
| 28.3.12 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1000 mm dia | Metre | 7,654.00 |
| 28.3.13 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1100 mm dia | Metre | 9,146.00 |
| 28.3.14 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1200 mm dia | Metre | 10,794.00 |
| 28.3.15 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1400 mm dia | Metre | 13,096.00 |
| 28.3.16 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1600 mm dia | Metre | 15,840.00 |
| 28.3.17 | Providing and Laying non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1800 mm dia Rate SI NO. Particulars of Items Unit | Metre | 19,229.00 |
| 28.4.1 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints150 mm dia | Metre | 128.00 |
| 28.4.2 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints250 mm dia | Metre | 185.00 |
| 28.4.3 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints300 mm dia | Metre | 240.00 |
| 28.4.4 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints350 mm dia | Metre | 387.00 |
| 28.4.5 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints400 mm dia | Metre | 406.00 |
| 28.4.6 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints450 mm dia | Metre | 499.00 |
| 28.4.7 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints500 mm dia | Metre | 535.00 |
| 28.4.8 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints600 mm dia | Metre | 636.00 |
| 28.4.9 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints700 mm dia | Metre | 726.00 |
| 28.4.10 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints800 mm dia | Metre | 835.00 |
| 28.4.11 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints900 mm dia | Metre | 1,017.00 |
| 28.4.12 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1000 mm dia | Metre | 1,163.00 |
| 28.4.13 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1100 mm dia | Metre | 1,217.00 |
| 28.4.14 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1200 mm dia | Metre | 1,308.00 |
| 28.4.15 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1400 mm dia | Metre | 1,670.00 |
| 28.4.16 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1600 mm dia | Metre | 1,997.00 |
| 28.4.17 | Labour only for laying and Jointing non-pressure (NP3) RCC socket & spigot pipes with rubber gasket joint including testing of joints1800 mm dia | Metre | 2,360.00 |
| 28.5.1 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints250 mm dia | Metre | 1,016.00 |
| 28.5.2 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints300 mm dia | Metre | 1,466.00 |
| 28.5.3 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints350 mm dia | Metre | 2,177.00 |
| 28.5.4 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints400 mm dia | Metre | 2,430.00 |
| 28.5.5 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints450 mm dia | Metre | 2,869.00 |
| 28.5.6 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints500 mm dia | Metre | 3,229.00 |
| 28.5.7 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints600 mm dia | Metre | 4,413.00 |
| 28.5.8 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints700 mm dia | Metre | 5,283.00 |
| 28.5.9 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints800 mm dia | Metre | 6,801.00 |
| 28.5.10 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints900 mm dia | Metre | 8,276.00 |
| 28.5.11 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1000 mm dia | Metre | 8,831.00 |
| 28.5.12 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1100 mm dia | Metre | 10,524.00 |
| 28.5.13 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1200 mm dia | Metre | 10,757.00 |
| 28.5.14 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1400 mm dia | Metre | 13,912.00 |
| 28.5.15 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1600 mm dia | Metre | 16,578.00 |
| 28.5.16 | Providing and laying non-pressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints1800 mm dia | Metre | 19,522.00 |
| 28.6.1 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit250 mm dia | Metre | 209.00 |
| 28.6.2 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit300 mm dia | Metre | 266.00 |
| 28.6.3 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit350 mm dia | Metre | 380.00 |
| 28.6.4 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit400 mm dia | Metre | 437.00 |
| 28.6.5 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit450 mm dia | Metre | 480.00 |
| 28.6.6 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit500 mm dia | Metre | 534.00 |
| 28.6.7 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit600 mm dia | Metre | 636.00 |
| 28.6.8 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit700 mm dia | Metre | 726.00 |
| 28.6.9 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit800 mm dia | Metre | 889.00 |
| 28.6.10 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit900 mm dia | Metre | 1,071.00 |
| 28.6.11 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1000 mm dia | Metre | 1,217.00 |
| 28.6.12 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1100 mm dia | Metre | 1,253.00 |
| 28.6.13 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1200 mm dia | Metre | 1,398.00 |
| 28.6.14 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1400 mm dia | Metre | 1,816.00 |
| 28.6.15 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1600 mm dia | Metre | 1,997.00 |
| 28.6.16 | Labour only for laying and jointing nonpressure (NP4) RCC socket & spigot pipes with rubber gasket joint including testing of joints. Rate SI NO. Particulars of Items Unit1800 mm dia | Metre | 2,360.00 |
| 28.7.1 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 306.00 |
| 28.7.2 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia | Metre | 415.00 |
| 28.7.3 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 520.00 |
| 28.7.4 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 568.00 |
| 28.7.5 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 645.00 |
| 28.7.6 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia | Metre | 775.00 |
| 28.7.7 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 903.00 |
| 28.7.8 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 1,021.00 |
| 28.7.9 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 1,092.00 |
| 28.7.10 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia | Metre | 1,677.00 |
| 28.7.11 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 2,221.00 |
| 28.7.12 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 2,846.00 |
| 28.7.13 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 3,360.00 |
| 28.7.14 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 4,023.00 |
| 28.7.15 | Providing, Laying & jointing non-pressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia | Metre | 4,746.00 |
| 28.8.1 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 81.00 |
| 28.8.2 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia Rate SI NO. Particulars of Items Unit | Metre | 130.00 |
| 28.8.3 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 134.00 |
| 28.8.4 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 126.00 |
| 28.8.5 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 161.00 |
| 28.8.6 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia | Metre | 170.00 |
| 28.8.7 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 176.00 |
| 28.8.8 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 187.00 |
| 28.8.9 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 209.00 |
| 28.8.10 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia | Metre | 233.00 |
| 28.8.11 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 253.00 |
| 28.8.12 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 297.00 |
| 28.8.13 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 364.00 |
| 28.8.14 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 460.00 |
| 28.8.15 | Labour only for laying & jointing nonpressure (NP2) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia | Metre | 574.00 |
| 28.9.1 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 437.00 |
| 28.9.2 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia | Metre | 651.00 |
| 28.9.3 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 694.00 |
| 28.9.4 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 756.00 |
| 28.9.5 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 1,209.00 |
| 28.9.6 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia | Metre | 1,648.00 |
| 28.9.7 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 1,759.00 |
| 28.9.8 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 2,193.00 |
| 28.9.9 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 2,280.00 |
| 28.9.10 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia | Metre | 3,639.00 |
| 28.9.11 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 3,910.00 |
| 28.9.12 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 4,610.00 |
| 28.9.13 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 5,124.00 |
| 28.9.14 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 6,408.00 |
| 28.9.15 | Providing, Laying & jointing non-pressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia | Metre | 7,608.00 |
| 28.10.1 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 81.00 |
| 28.10.2 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia | Metre | 130.00 |
| 28.10.3 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 134.00 |
| 28.10.4 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 126.00 |
| 28.10.5 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 161.00 |
| 28.10.6 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia Rate SI NO. Particulars of Items Unit | Metre | 170.00 |
| 28.10.7 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 176.00 |
| 28.10.8 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 187.00 |
| 28.10.9 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 209.00 |
| 28.10.10 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia | Metre | 233.00 |
| 28.10.11 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 253.00 |
| 28.10.12 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 297.00 |
| 28.10.13 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 364.00 |
| 28.10.14 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 460.00 |
| 28.10.15 | Labour only for laying & jointing nonpressure (NP3) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia | Metre | 574.00 |
| 28.11.1 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 449.00 |
| 28.11.2 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia | Metre | 656.00 |
| 28.11.3 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 737.00 |
| 28.11.4 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 997.00 |
| 28.11.5 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 1,663.00 |
| 28.11.6 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia | Metre | 1,857.00 |
| 28.11.7 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 1,947.00 |
| 28.11.8 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 2,314.00 |
| 28.11.9 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 2,989.00 |
| 28.11.10 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia | Metre | 3,676.00 |
| 28.11.11 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 4,589.00 |
| 28.11.12 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 5,744.00 |
| 28.11.13 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 6,401.00 |
| 28.11.14 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 7,470.00 |
| 28.11.15 | Providing, Laying & jointing non-pressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia | Metre | 7,879.00 |
| 28.12.1 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints150 mm dia | Metre | 81.00 |
| 28.12.2 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints200 mm dia | Metre | 130.00 |
| 28.12.3 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints250 mm dia | Metre | 134.00 |
| 28.12.4 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints300 mm dia | Metre | 126.00 |
| 28.12.5 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints350 mm dia | Metre | 161.00 |
| 28.12.6 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints400 mm dia | Metre | 170.00 |
| 28.12.7 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints450 mm dia | Metre | 176.00 |
| 28.12.8 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints500 mm dia | Metre | 187.00 |
| 28.12.9 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints600 mm dia | Metre | 209.00 |
| 28.12.10 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints700 mm dia Rate SI NO. Particulars of Items Unit | Metre | 233.00 |
| 28.12.11 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints800 mm dia | Metre | 253.00 |
| 28.12.12 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints900 mm dia | Metre | 297.00 |
| 28.12.13 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1000 mm dia | Metre | 364.00 |
| 28.12.14 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1100 mm dia | Metre | 460.00 |
| 28.12.15 | Labour only for Laying & jointing nonpressure (NP4) RCC pipes with collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 cement: 2 sand ) including testing of joints1200 mm dia SALT GLAZED STONEWARE PIPES, SEWER APPURTENANCES & SEWERAGES MAINTENANCE SALT GLAZED STONEWARE PIPES, SEWER APPURTENANCES NOTES: 1. Salt Glazed Stoneware 29.1. The salt Glazed stoneware pipe shall be conforming to IS:651:2007 29.2. The laying to S.W. pipes shall be done as per IS - 4127:1983 29.3. The bedding of the S. W. pipes shall be as per the specification given in the CPHEEO manual of sewerage & sewage treatment, payment for which shall be made as per chapter - 15 allied civil works. 29.4. The testing of the sewer line & refilling shall be done as per CPHEEO manual on sewerage and sewage management 29.5. In order to avoid damage to the pipes and especially to the spigot end, pipes shall not be dragged along concrete and similar pavements with hard surfaces. 29.6. The pipes and fittings shall be inspected for defects and be rung with a light hammer preferable while suspended to detect cracks. 29.7. All lumps, blisters and excess coating materials shall be removed gently from the socket and spigot of each pipe. The outside of the spigot and the inside of the socket shall be wiped clean and dry before the pipe is laid. 29.8. In shallow trenches, manual handing is enough but in deep trenches, they shall be lowered into the trench by means of ropes. Under no circumstances the pipe shall be dropped or dumped into the trench. 29.9. Every precaution shall be taken to prevent foreign material from entering the pipe when it is being placed in the line. 29.10. The pipe between two manholes shall be laid truly in a straight line without vertical and horizontal undulations. The pipe shall be laid true to line and grade as specified in the relevant specifications 29.2. Unloading of pipes | Metre | 574.00 |
S-02/SOURCE RECORD2023
- ISSUED BY
- Madhya Pradesh Public Health Engineering Department (PHED)
- EFFECTIVE
- 2023-09-01
- RETRIEVED
- 2026-07-29
S-03/CHAPTERS20 MORE
Other chapters in this schedule
- Ductile Iron Pressure Pipes and Specials with Tyton Joints and DI Valve669
- Polyethylene Pipe and Fittings209
- Galvanized Iron Pipes, Specials and Gun Metal or Brass Fittings354
- Oriented P.V.C. (PVC-O) Pipes13
- M.S. Pipes, Specials, Fittings including Fabrication & Laying75
- Asbestos Cement Pressure Pipes and Cast Iron Fittings16
- Bar Wrapped Steel Cylinder Pipes (BWSC)270
- Cast Iron Socket and Spigot Pipes & Specials with Lead Joints, Tyton Joints, Cast Iron Pipes & Specials with Flanged Joints, Cast Iron Valves, Sluice Gate & Air Valves351
- Consumer Service Connection131
- Water Hammer Devices96
- Pumps172
- Measuring Devices40
SHOW ALL 20 CHAPTERS
- Miscellaneous (Water Supply)73
- Allied Civil Works82
- Intake Well Related Works27
- Ground Service Reservoir & Sump Tanks (GSR)19
- Construction of Gravel Packed Tube Well5
- Development, Yield Test and Disinfection of Tube Well6
- Unplasticized Non-Pressure Polyvinyl Chloride (PVC-U) Pipes, Double Wall Corrugated (DWC) Pipes for Use in Underground Sewerage System32
- Salt Glazed Stoneware Pipes, Sewer Appurtenances & Sewerage Maintenance126
ARCHED / ESTIMATING
Pricing reinforced cement concrete pipes against a live tender
Mapping a tender BOQ to the right schedule items, applying the current cost index and catching where rates have moved since the base edition takes time and is easy to get wrong. We can do it for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.