80 rates for labour items from the Tamil Nadu Water Supply and Drainage (TWAD) Board, effective 2024-01-23.

Rates for Labour rates in the Tamil Nadu Water Works Schedule of Rates 2023-24 run from ₹513.00 to ₹1,216.00. Transcribed from Tamil Nadu TWAD Board — Standard Schedule of Rates 2023-24, effective 23 January 2024. Reference only — verify against the official source before pricing a bid.

80 items — scroll the table to browse

DescriptionUnit
1Technical Assistant Gr.I (BE passed)Day1,216.00
3Technical Assistant Gr.III (Diploma inDay926.00
4Engg. Failed / ITI (Civil) passedLaboratory Assistant. Gr.IDay926.00
5Laboratory Assistant. Gr.II (Degree in Science/Day849.00
6Laboratory Assistant Grade III (with Degree qualification to work as works clerk)Day763.00
7B.Sc., (Agriculture) Passed- Technical AssistantDay1,096.00
8Computer Operator Gr.I [B.E. (ComputerDay1,216.00
9Computer Operator Gr.II [B.Sc., (ComputerDay1,096.00
10Wireman Grade I/ Electrician Grade IDay826.00
12Irrigation Community Organiser Grade IIDay976.00
13SKILLED CATEGORYBlacksmith - 1st ClassDay769.00
14SKILLED CATEGORYCarpenter I ClassDay976.00
15SKILLED CATEGORYCleaner I GrDay519.00
16SKILLED CATEGORYFitter I ClassDay881.00
17Fitter (Pipe laying / Bar bending) I ClassDay866.00
18SKILLED CATEGORYFloor PolisherDay769.00
19SKILLED CATEGORYHammer MazdoorDay618.00
20SKILLED CATEGORYDriver (Light duty)Day769.00
21SKILLED CATEGORYDriver (Heavy duty)Day820.00
24Mason for Brick Work - I ClassDay999.00
25Mason for Stone Work - I ClassDay999.00
26Mechanic - 1st ClassDay769.00
27Painter/Varnisher-I ClassDay797.00
29Plumber I ClassDay866.00
31Smith 1st ClassDay766.00
32Stone cutter- I ClassDay766.00
33Syrang-1st ClassDay766.00
34Tinker 1 st ClassDay618.00
35Turner 1 st ClassDay708.00
36Time Keeper Ist ClassDay766.00
37Welder/ Bracer - I ClassDay766.00
39Compressor OperatorDay677.00
40Geological AssistantDay947.00
41Stone & Crusher OperatorDay677.00
42Wireman Grade II/ Electrician Grade IIDay820.00
43Lift OperatorDay740.00
44Laboratory AttendantDay551.00
45Sound Service OperatorDay618.00
46Electrical MaistryDay947.00
47Boat MazdoorDay644.00
48Head Mazdoor for Well sinkingDay644.00
49Moplah - I ClassDay766.00
50Navagonies or Javali Man - 1st ClassDay644.00
51Well Diver for removing silt - 1 st ClassDay766.00
52Well sinker - 1st ClassDay866.00
54SEMI SKILLED CATEGORYAxe MazdoorDay608.00
55SEMI SKILLED CATEGORYBlacksmith - 2nd ClassDay738.00
56Bullocks pair with driver (with bandy)Day1,204.00
57Bullocks single with driver (with bandy)Day866.00
58SEMI SKILLED CATEGORYCarpenter II ClassDay932.00
59SEMI SKILLED CATEGORYCleaner II GrDay513.00
60SEMI SKILLED CATEGORYFitter II ClassDay856.00
61Fitter (Pipe laying / Bar bending) II ClassDay839.00
63Jumper MazdoorDay608.00
64Mason for Brick Work - II ClassDay932.00
65Mason for Stone Work - II ClassDay932.00
66Mazdoor Category IDay651.00
67Head MazdoorDay674.00
68Mechanic - 2nd ClassDay738.00
69Painter/Varnisher-II ClassDay772.00
70Plumber II ClassDay839.00
72Smith 2nd ClassDay738.00
73Stone cutter- II ClassDay738.00
74Syrang-2 nd ClassDay738.00
76Tinker 2 nd ClassDay608.00
77Turner 2 nd ClassDay674.00
78Time Keeper 2nd ClassDay738.00
79Welder/ Bracer - II ClassDay738.00
80Mazdoor employed for Geological mapingDay652.00
82Sampling and Drilling worksMazdoor employed for GeophysicalDay652.00
83Head Mazdoor to supervise exploratory worksDay688.00
84Mixer Operator (including concrete mixer )Day708.00
85Investigation worksMixer DriverDay674.00
86Investigation worksHeavy MazdoorDay708.00
87Investigation worksElectrical HelperDay644.00
88Investigation worksFerry MazdoorDay674.00
89Investigation worksMoplah - II ClassDay738.00
90Well Diver for removing silt - 2nd ClassDay738.00
91Investigation worksWell sinker - 2nd ClassDay839.00
92UN- SKILLED CATEGORYMazdoor Category IIDay534.00

Pricing rates for labour against a live tender

Mapping a tender BOQ to the right schedule items, applying the current cost index, and catching where rates have moved since the base edition is slow and easy to get wrong. Arched's estimation engine reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.