AP SOR 2026-27: Andhra Pradesh Has One Common Schedule, Split Into Four Parts
Andhra Pradesh's SOR 2026-27 is real and current — effective 1 June 2026. But it is one Common Schedule for every engineering department, divided into four Parts, and Part-III prices materials rather than civil items of work. Which Part you need, and what is not in it.
Search for ap sor 2026-27 and you will get a mix of results for a document most states do not have. The edition is real: Andhra Pradesh's Common Schedule of Rates 2026-27 took effect on 1 June 2026. That already makes it an outlier — searches for a 2026-27 schedule in most states are looking for something that has not been published.
The difficulty is not finding it. It is that Andhra Pradesh publishes rates in a shape that does not match what the search asks for, in two ways: there is no PWD schedule, and the Part most people land on does not contain the rates they came for.
There is no AP PWD SOR — there is one Common Schedule
The schedule is issued by the Board of Chief Engineers, Government of Andhra Pradesh, and applies across engineering departments rather than belonging to one of them. This is why ap pwd schedule of rates returns nothing useful: the state does not publish a PWD book to find.
That is a different arrangement from most states, and worth holding onto when a tender document cites "the SOR" without qualification. In Andhra Pradesh, the unqualified reference is to the Common Schedule of Rates for the current year — currently 2026-27 — and the specificity you need comes from the Part, not the department.
Four Parts, one edition
| Part | Covers |
|---|---|
| Part-I | Water Resources |
| Part-II | Roads & Bridges |
| Part-III | Buildings, Water Supply & Electrical |
| Part-IV | Public Health |
These are Parts of a single edition, not four independent schedules. The edition year and the 1 June 2026 effective date are common to all of them, so there is no situation in which Part-II is on a newer book than Part-III.
As always, the edition named in the tender document governs. If a notice issued in May 2026 cites the previous edition, that is the book, whatever has since taken effect.
What Part-III actually prices — and what it does not
This is the part that surprises people, and it is worth stating plainly because nothing on the search results page tells you.
Part-III of the 2026-27 edition runs to 3,247 rate items across 97 chapters. Across all 97 chapter headings there is no chapter for earthwork, concrete, RCC, masonry, plastering or excavation. Not a thin chapter — no chapter.
What is there, grouped by content:
| Content group | Items | Chapters | Examples |
|---|---|---|---|
| Building materials | 939 | 21 | Bricks & Building Blocks, Steel Materials, Timber & Roofing Materials, Glass Materials, Wall & Floor Tiles, Paints & Polishes, Plywoods, Laminates & Veneers |
| Water supply & sanitary items | 486 | 9 | G.I. Pipes & Fittings, S.W.G. Pipes & Fittings, Taps & Faucets, Vitreous Chinaware Sanitary Appliances, Man Holes & Inspection Chambers |
| Electrical & services materials | 1,286 | 49 | U.G. Cables, Panel Mounting MCCBs, Pumpsets, Air Conditioners, LED Luminaires Indoor, Local Area Network |
| Electrical installation items | 536 | 43 | Overhead Lines & Line Materials, T.W. Boards, Lifts (new Installation), HVAC Systems (VRV/VRF), Fire Hydrant and Sprinkler System, Earthing |
The units confirm the shape. Of the 3,247 items, 1,242 are priced per number, 639 per each, 629 per square metre and 344 per running metre. Twenty-two are priced per cubic metre. A book that rates civil work does not look like that.
So Part-III is a basic-rates and finished-items book: it tells you what a thousand bricks cost, what a 25 mm G.I. pipe costs laid and tested, and what a lift installation costs. It does not tell you the rate for a cubic metre of M25 concrete.
Where the civil rates come from instead
The Common Schedule is derived from the A.P. Revised Standard Data, and that is where the build-up for a civil item of work lives — the quantities of labour, material and machinery that, combined with the basic rates in the schedule, produce a rate for the item. The relationship is the same one Odisha runs between its SOR 2022 and its Analysis of Rates 2006, and the same one CPWD runs between the DSR and its analysis volume.
The practical consequence: if your BOQ line is earthwork or concrete, looking it up in Part-III and finding nothing is the expected result, not a bad download. You are in the wrong instrument.
Which Part your work sits in
A building contract with internal water supply and electrical work is entirely inside Part-III — but only for the materials and the services items. Its civil lines still route through the Standard Data. A road contract sits in Part-II. An irrigation contract sits in Part-I. Public health engineering work sits in Part-IV.
Most estimating errors in Andhra Pradesh come from a mixed-scope contract whose lines belong to two Parts, priced as though they belonged to one.
The searchable Part-III rates
This site holds a transcription of Part-III of the 2026-27 edition as a searchable table with the chapter structure intact, so you can check a rate without opening the PDF: Andhra Pradesh Common Schedule of Rates 2026-27, Part-III — 3,247 items across 97 chapters, with Excel and CSV downloads carrying the source and retrieval date in their headers.
Parts I, II and IV are not transcribed here. For those, go to the official source.
Pricing an Andhra Pradesh tender
Andhra Pradesh is, on paper, one of the easier states to price: a current edition, one issuing authority, and a clean four-Part split. The difficulty is downstream of that. A tender's BOQ arrives in the contractor's line order, not the schedule's, and the work is deciding for each line which Part applies, whether the rate is a lookup or a Standard Data build-up, and what a rate fixed on 1 June 2026 is worth against inputs today.
If you are new to converting a schedule into a priced bill, how a schedule of rates differs from a bill of quantities covers the mechanics. Telangana's schedule is the closest comparison — the two states split a common inheritance and now publish differently — and Karnataka shows a third arrangement again, with district-wise volumes under a single state schedule.