Skip to main content
R/DAR 2023

Providing and fixing aluminium tower bolts, ISI marked, anodised (anodic coating not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or shade, with necessary screws etc. complete

300x10 mm
Item number
9.97.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹130.10/ NO
D-01/RATE ANALYSISITEM 9.97.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.97.1 (Providing and fixing aluminium tower bolts, ISI marked, anodised (anodic coating not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or shade, with necessary screws etc. complete : 300x10 mm) is derived from 4 priced inputs for 10 nos and works out to ₹130.10 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.97.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0698MATAnodised Aluminium tower bolt (barrel type)300x10 mmAnodised Aluminium tower bolt (barrel type) 300x10 mm10 Nos1610.00610.00
0587MATChromium plated Brass screws 30 mm100 Nos0.8228.00182.40
9977MATCarriage of materialsL.S.4.422.2710.03
0111LABCarpenter 1st classday0.125897.00112.13
BUILD-UP TO RATE
TOTAL
914.56
Add 1 % Water charges on “W”
+9.15
TOTAL
923.71
Add GST on “X” (multiplying factor 0.2127)
+196.47
TOTAL
1,120.18
Add 15% CPOH on “Y”
+168.03
TOTAL
1,288.21
Add Cess @ 1% on “Z”
+12.88
Cost of 10 nos
1,301.09
Cost of 1 no
130.11
SAY
₹130.10
D-02/SOURCEPRINTED PAGE 566
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
566

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 566. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.