Providing and fixing aluminium sliding door bolts, ISI marked anodised (anodic coating not less than grade AC 10 as per IS : 1868), transparent or dyed to required colour or shade, with nuts and screws etc. complete

250x16 mm
Item number
9.96.2
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹260.60/ NO
D-01/RATE ANALYSISITEM 9.96.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.96.2 (Providing and fixing aluminium sliding door bolts, ISI marked anodised (anodic coating not less than grade AC 10 as per IS : 1868), transparent or dyed to required colour or shade, with nuts and screws etc. complete : 250x16 mm) is derived from 4 priced inputs for 10 nos and works out to ₹260.60 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.96.2DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0697MATAnodised Aluminium sliding door bolt 250x16 mmeach10130.001,300.00
0588MATChromium plated Brass screws 25 mm100 Nos0.4177.0070.80
9977MATCarriage of materialsL.S.5.462.2712.39
0111LABCarpenter 1st classday0.5897.00448.50
BUILD-UP TO RATE
TOTAL
1,831.69
Add 1 % Water charges on “W”
+18.32
TOTAL
1,850.01
Add GST on “X” (multiplying factor 0.2127)
+393.50
TOTAL
2,243.51
Add 15% CPOH on “Y”
+336.53
TOTAL
2,580.04
Add Cess @ 1% on “Z”
+25.80
Cost of 10 nos
2,605.84
Cost of 1 no
260.58
SAY
₹260.60
D-02/SOURCEPRINTED PAGE 565
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
565

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 565. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.