Providing and fixing aluminium sliding door bolts, ISI marked anodised (anodic coating not less than grade AC 10 as per IS : 1868), transparent or dyed to required colour or shade, with nuts and screws etc. complete
- Item number
- 9.96.2
- Analysis basis
- 10 nos
- Priced inputs
- 4
- Derived rate
- ₹260.60/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.96.2 (Providing and fixing aluminium sliding door bolts, ISI marked anodised (anodic coating not less than grade AC 10 as per IS : 1868), transparent or dyed to required colour or shade, with nuts and screws etc. complete : 250x16 mm) is derived from 4 priced inputs for 10 nos and works out to ₹260.60 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0697 | MAT | Anodised Aluminium sliding door bolt 250x16 mm | each | 10 | 130.00 | 1,300.00 |
| 0588 | MAT | Chromium plated Brass screws 25 mm | 100 Nos | 0.4 | 177.00 | 70.80 |
| 9977 | MAT | Carriage of materials | L.S. | 5.46 | 2.27 | 12.39 |
| 0111 | LAB | Carpenter 1st class | day | 0.5 | 897.00 | 448.50 |
- TOTAL
- 1,831.69
- Add 1 % Water charges on “W”
- +18.32
- TOTAL
- 1,850.01
- Add GST on “X” (multiplying factor 0.2127)
- +393.50
- TOTAL
- 2,243.51
- Add 15% CPOH on “Y”
- +336.53
- TOTAL
- 2,580.04
- Add Cess @ 1% on “Z”
- +25.80
- Cost of 10 nos
- 2,605.84
- Cost of 1 no
- 260.58
- SAY
- ₹260.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 565
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 565. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.