Providing and fixing ISI marked, IS : 1341, M.S. heavy weight bright finished butt hinges with necessary screws etc. complete

75x60x3.10 mm
Item number
9.56.3
Analysis basis
ten hinges
Priced inputs
5
Derived rate
₹48.15/ NO
D-01/RATE ANALYSISITEM 9.56.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.56.3 (Providing and fixing ISI marked, IS : 1341, M.S. heavy weight bright finished butt hinges with necessary screws etc. complete : 75x60x3.10 mm) is derived from 5 priced inputs for ten hinges and works out to ₹48.15 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.56.3DETAILS OF COST FOR TEN HINGES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8224MATM.S. heavy weight butt hinges 75x60x3.1 mm IS: 1341 marked10 Nos1125.00125.00
0638MATBright finished or black enamelled mild steel screws 30 mmBright finished or black enameled mild steel screws 30 mm100 Nos0.648.0028.80
9977MATCarriage of materialsL.S.1.822.274.13
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
338.41
Add 1 % Water charges on “W”
+3.38
TOTAL
341.79
Add GST on “X” (multiplying factor 0.2127)
+72.70
TOTAL
414.49
Add 15% CPOH on “Y”
+62.17
TOTAL
476.66
Add Cess @ 1% on “Z”
+4.77
Cost of 10 nos.
481.43
Cost of 1 no
48.14
SAY
₹48.15
D-02/SOURCEPRINTED PAGE 512
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
512

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 512. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.