Providing and fixing ISI marked, IS : 1341, M.S. heavy weight bright finished butt hinges with necessary screws etc. complete

50x40x2.50 mm
Item number
9.56.4
Analysis basis
ten hinges
Priced inputs
4
Derived rate
₹27.50/ NO
D-01/RATE ANALYSISITEM 9.56.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.56.4 (Providing and fixing ISI marked, IS : 1341, M.S. heavy weight bright finished butt hinges with necessary screws etc. complete : 50x40x2.50 mm) is derived from 4 priced inputs for ten hinges and works out to ₹27.50 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.56.4DETAILS OF COST FOR TEN HINGES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8225MATM.S. heavy weight butt hinges 50x40x2.5 mm IS : 1341 marked10 Nos1110.00110.00
0640MATBright finished or black enamelled mild steel screws 20 mmBright finished or black enameled mild steel screws 20 mm100 Nos0.440.0016.00
9977MATCarriage of materialsL.S.0.912.272.07
0112LABCarpenter 2nd classday0.08816.0065.28
BUILD-UP TO RATE
TOTAL
193.35
Add 1 % Water charges on “W”
+1.93
TOTAL
195.28
Add GST on “X” (multiplying factor 0.2127)
+41.54
TOTAL
236.82
Add 15% CPOH on “Y”
+35.52
TOTAL
272.34
Add Cess @ 1% on “Z”
+2.72
Cost of 10 nos.
275.06
Cost of 1 no
27.51
SAY
₹27.50
D-02/SOURCEPRINTED PAGE 513
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
513

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 513. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.