Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete

125x65x2.12 mm
Item number
9.55.1
Analysis basis
ten hinges
Priced inputs
5
Derived rate
₹53.00/ NO
D-01/RATE ANALYSISITEM 9.55.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.55.1 (Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete : 125x65x2.12 mm) is derived from 5 priced inputs for ten hinges and works out to ₹53.00 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.55.1DETAILS OF COST FOR TEN HINGES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0594MATBright finished or black enamelled mild steel butt hinges 125x65x2.12 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 125x65x 2.12 mm10 Nos1122.00122.00
0635MATBright finished or black enamelled ISI marked IS: 1341 mild steel pressed screws 50 mmBright finished or black enameled mild steel screws 50 mm100 Nos0.880.0064.00
9977MATCarriage of materialsL.S.2.732.276.20
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
372.68
Add 1 % Water charges on “W”
+3.73
TOTAL
376.41
Add GST on “X” (multiplying factor 0.2127)
+80.06
TOTAL
456.47
Add 15% CPOH on “Y”
+68.47
TOTAL
524.94
Add Cess @ 1% on “Z”
+5.25
Cost of 10 nos.
530.19
Cost of 1 no
53.02
SAY
₹53.00
D-02/SOURCEPRINTED PAGE 509
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
509

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 509. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.