Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete
- Item number
- 9.55.1
- Analysis basis
- ten hinges
- Priced inputs
- 5
- Derived rate
- ₹53.00/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.55.1 (Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete : 125x65x2.12 mm) is derived from 5 priced inputs for ten hinges and works out to ₹53.00 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0594 | MAT | Bright finished or black enamelled mild steel butt hinges 125x65x2.12 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 125x65x 2.12 mm | 10 Nos | 1 | 122.00 | 122.00 |
| 0635 | MAT | Bright finished or black enamelled ISI marked IS: 1341 mild steel pressed screws 50 mmBright finished or black enameled mild steel screws 50 mm | 100 Nos | 0.8 | 80.00 | 64.00 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0112 | LAB | Carpenter 2nd class | day | 0.14 | 816.00 | 114.24 |
| 0114 | LAB | Beldar | day | 0.09 | 736.00 | 66.24 |
- TOTAL
- 372.68
- Add 1 % Water charges on “W”
- +3.73
- TOTAL
- 376.41
- Add GST on “X” (multiplying factor 0.2127)
- +80.06
- TOTAL
- 456.47
- Add 15% CPOH on “Y”
- +68.47
- TOTAL
- 524.94
- Add Cess @ 1% on “Z”
- +5.25
- Cost of 10 nos.
- 530.19
- Cost of 1 no
- 53.02
- SAY
- ₹53.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 509
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 509. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.