Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete

100x58x1.90 mm
Item number
9.55.2
Analysis basis
ten hinges
Priced inputs
5
Derived rate
₹45.00/ NO
D-01/RATE ANALYSISITEM 9.55.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.55.2 (Providing and fixing ISI marked IS:1341 M.S. pressed butt hinges bright finished with necessary screws etc. complete : 100x58x1.90 mm) is derived from 5 priced inputs for ten hinges and works out to ₹45.00 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.55.2DETAILS OF COST FOR TEN HINGES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0595MATBright finished or black enamelled ISI marked IS: 1341 mild steel pressed butt hinges 100x58x1.90 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 100x58x 1.90 mm10 Nos180.0080.00
0637MATBright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mm100 Nos0.862.0049.60
9977MATCarriage of materialsL.S.2.732.276.20
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
316.28
Add 1 % Water charges on “W”
+3.16
TOTAL
319.44
Add GST on “X” (multiplying factor 0.2127)
+67.94
TOTAL
387.38
Add 15% CPOH on “Y”
+58.11
TOTAL
445.49
Add Cess @ 1% on “Z”
+4.45
Cost of 10 nos.
449.94
Cost of 1 no
44.99
SAY
₹45.00
D-02/SOURCEPRINTED PAGE 510
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
510

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 510. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK