Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)

Item number
9.53
Analysis basis
1 hold
Priced inputs
7
Derived rate
₹228.85/ HOLD
D-01/RATE ANALYSISITEM 9.53

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.53 (Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)) is derived from 7 priced inputs for 1 hold and works out to ₹228.85 per hold after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • M.S.flat 40x5mm 40cm long @ 1.68 kg/m =
  • 0.672 kg = 0.007 qunital
  • Cement concrete 1:3:6
  • 30x10x15cm= 0.0045cum.+
  • Total = 0.00495cum. Say 0.005cum.
  • Add wastage @ 10% = 0.00045cum.
ANALYSIS OF RATES · ITEM 9.53DETAILS OF COST FOR 1 HOLD FAST
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.0075,450.0038.15
9977MATCarriage of steelL.S.1.822.274.13
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.0059,311.4046.56
9999MATBolts and nutsL.S.5.462.2712.39
0103LABBlacksmith 2nd classday0.03816.0024.48
0123LABMason (brick layer) 1st classMason 1st classday0.03897.0026.91
0114LABBeldarday0.03736.0022.08
BUILD-UP TO RATE
TOTAL
174.70
Add 1 % Water charges on “W-A”
+1.28
TOTAL
175.98
Add GST on “X-A” (multiplying factor 0.2127)
+27.53
TOTAL
203.51
Add 15% CPOH on “Y-A”
+23.54
TOTAL
227.05
Add Cess @ 1% on “Z-A”
+1.80
Cost for 1 no
228.85
SAY
₹228.85
D-02/SOURCEPRINTED PAGE 507
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
507

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 507. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.