Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)
- Item number
- 9.53
- Analysis basis
- 1 hold
- Priced inputs
- 7
- Derived rate
- ₹228.85/ HOLD
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.53 (Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)) is derived from 7 priced inputs for 1 hold and works out to ₹228.85 per hold after water charges, GST, CPOH and cess. The full build-up is below.
- M.S.flat 40x5mm 40cm long @ 1.68 kg/m =
- 0.672 kg = 0.007 qunital
- Cement concrete 1:3:6
- 30x10x15cm= 0.0045cum.+
- Total = 0.00495cum. Say 0.005cum.
- Add wastage @ 10% = 0.00045cum.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1008 | MAT | Flats upto 10 mm in thicknessFlats up to 10 mm in thickness | quintal | 0.007 | 5,450.00 | 38.15 |
| 9977 | MAT | Carriage of steel | L.S. | 1.82 | 2.27 | 4.13 |
| SUB | Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5 | cum | 0.005 | 9,311.40 | 46.56 | |
| 9999 | MAT | Bolts and nuts | L.S. | 5.46 | 2.27 | 12.39 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.03 | 816.00 | 24.48 |
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.03 | 897.00 | 26.91 |
| 0114 | LAB | Beldar | day | 0.03 | 736.00 | 22.08 |
- TOTAL
- 174.70
- Add 1 % Water charges on “W-A”
- +1.28
- TOTAL
- 175.98
- Add GST on “X-A” (multiplying factor 0.2127)
- +27.53
- TOTAL
- 203.51
- Add 15% CPOH on “Y-A”
- +23.54
- TOTAL
- 227.05
- Add Cess @ 1% on “Z-A”
- +1.80
- Cost for 1 no
- 228.85
- SAY
- ₹228.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 507
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 507. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.