CPWD Analysis of Rates · Wood and PVC Work

Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)

Item number
9.53
Analysis basis
Details of cost for 1 hold fast
Priced inputs
7
Derived rate
228.85 / hold

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.53 Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size) — is derived from 7 priced inputs for 1 hold and works out to ₹228.85 per hold after water charges, GST, CPOH and cess. The full build-up is below.

  • M.S.flat 40x5mm 40cm long @ 1.68 kg/m =
  • 0.672 kg = 0.007 qunital
  • Cement concrete 1:3:6
  • 30x10x15cm= 0.0045cum.+
  • Total = 0.00495cum. Say 0.005cum.
  • Add wastage @ 10% = 0.00045cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1008Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterialquintal0.0075,450.0038.15
9977Carriage of steelMaterialL.S.1.822.274.13
Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysiscum0.0059,311.4046.56
9999Bolts and nutsMaterialL.S.5.462.2712.39
0103Blacksmith 2nd classLabourday0.03816.0024.48
0123Mason (brick layer) 1st classMason 1st classLabourday0.03897.0026.91
0114BeldarLabourday0.03736.0022.08
TOTAL
174.70
Add 1 % Water charges on “W-A”
1.28
TOTAL
175.98
Add GST on “X-A” (multiplying factor 0.2127)
27.53
TOTAL
203.51
Add 15% CPOH on “Y-A”
23.54
TOTAL
227.05
Add Cess @ 1% on “Z-A”
1.80
Cost for 1 no
228.85
Say
228.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 507. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.