CPWD Analysis of Rates · Wood and PVC Work
Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)
- Item number
- 9.53
- Analysis basis
- Details of cost for 1 hold fast
- Priced inputs
- 7
- Derived rate
- ₹228.85 / hold
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.53 — Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size) — is derived from 7 priced inputs for 1 hold and works out to ₹228.85 per hold after water charges, GST, CPOH and cess. The full build-up is below.
- M.S.flat 40x5mm 40cm long @ 1.68 kg/m =
- 0.672 kg = 0.007 qunital
- Cement concrete 1:3:6
- 30x10x15cm= 0.0045cum.+
- Total = 0.00495cum. Say 0.005cum.
- Add wastage @ 10% = 0.00045cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 0.007 | 5,450.00 | 38.15 |
| 9977 | Carriage of steelMaterial | L.S. | 1.82 | 2.27 | 4.13 |
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.005 | 9,311.40 | 46.56 | |
| 9999 | Bolts and nutsMaterial | L.S. | 5.46 | 2.27 | 12.39 |
| 0103 | Blacksmith 2nd classLabour | day | 0.03 | 816.00 | 24.48 |
| 0123 | Mason (brick layer) 1st classMason 1st classLabour | day | 0.03 | 897.00 | 26.91 |
| 0114 | BeldarLabour | day | 0.03 | 736.00 | 22.08 |
- TOTAL
- 174.70
- Add 1 % Water charges on “W-A”
- 1.28
- TOTAL
- 175.98
- Add GST on “X-A” (multiplying factor 0.2127)
- 27.53
- TOTAL
- 203.51
- Add 15% CPOH on “Y-A”
- 23.54
- TOTAL
- 227.05
- Add Cess @ 1% on “Z-A”
- 1.80
- Cost for 1 no
- 228.85
- Say
- 228.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 507. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.