R/DAR 2023

Deduct for fixing 75x25 mm hard drawn steel wire fabric of weight not less than 7.75 Kg per sqm in panelled and glazed door and window shutter instead of glass sheet 4 mm thick (weight not less than 10 kg per sqm)

Item number
9.52
Analysis basis
1 sqm
Priced inputs
2
Derived rate
₹155.10/ SQM
D-01/RATE ANALYSISITEM 9.52

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.52 (Deduct for fixing 75x25 mm hard drawn steel wire fabric of weight not less than 7.75 Kg per sqm in panelled and glazed door and window shutter instead of glass sheet 4 mm thick (weight not less than 10 kg per sqm)) is derived from 2 priced inputs for 1 sqm and works out to ₹155.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Difference of cost
ANALYSIS OF RATES · ITEM 9.52DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1021MATHard drawn steel wire fabricHard drawn steel wire fabric 75 x 25 mm mesh of weight not less than 7.75 kg/sqmsqm1430.00430.00
2406MATFloat glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)sqm-1321.00-321.00
BUILD-UP TO RATE
TOTAL
109.00
Add 1 % Water charges on “W”
+1.09
TOTAL
110.09
Add GST on “X” (multiplying factor 0.2127)
+23.42
TOTAL
133.51
Add 15% CPOH on “Y”
+20.03
TOTAL
153.54
Add Cess @ 1% on “Z”
+1.54
Extra cost for 1 sqm.
155.08
SAY
₹155.10
D-02/SOURCEPRINTED PAGE 507
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
507

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 507. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.