CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete
With 12 mm mild steel U beading
- Item number
- 9.51.2
- Analysis basis
- Details of cost for a window of size 140x110cm
- Priced inputs
- 6
- Derived rate
- ₹939.20 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.51.2 — Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete With 12 mm mild steel U beading — is derived from 6 priced inputs for a window and works out to ₹939.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- =1.54sqm.
- Wire gauze -20x60mm mesh 3.2mm wide =
- 1.4x1.1m = 1.54sqm.+
- Total = 1.69 sqm.
- Add wastage @ 10% = 0.15sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7029 | Galvanised wire mesh of average width of aperture 1.4 mm and nominal dia. Of wire 0.63 mmGalvanised wire mesh of average width of aperture 1.4 mm and nominal dia of wire 0.63 mmMaterial | sqm | 1.69 | 260.00 | 439.40 |
| 9977 | Carriage of wire fabricMaterial | L.S. | 1.82 | 2.27 | 4.13 |
| 7349 | 12 mm M.S. ‘U’ beadingMaterial | metre | 5 | 15.00 | 75.00 |
| 0112 | Carpenter 2nd classLabour | day | 0.33 | 816.00 | 269.28 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 9999 | SundriesMaterial | L.S. | 19.76 | 2.27 | 44.86 |
- TOTAL
- 1,016.67
- Add 1 % Water charges on “W”
- 10.17
- TOTAL
- 1,026.84
- Add GST on “X” (multiplying factor 0.2127)
- 218.41
- TOTAL
- 1,245.25
- Add 15% CPOH on “Y”
- 186.79
- TOTAL
- 1,432.04
- Add Cess @ 1% on “Z”
- 14.32
- Cost of 1.54 sqm.
- 1,446.36
- Cost of 1 sqm.
- 939.19
- Say
- 939.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 506. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.