Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete

With second class teak wood beading 62X19 mm

Item number
9.51.1
Analysis basis
Details of cost for a window of size 140x110cm
Priced inputs
6
Derived rate
1,308.35 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.51.1 Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete With second class teak wood beading 62X19 mm — is derived from 6 priced inputs for a window and works out to ₹1,308.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • =1.54sqm.
  • Wire gauze -20x60mm mesh 3.2mm wide =
  • 1.4x1.1m = 1.54sqm.+
  • Total = 1.69 sqm.
  • Second class teak wood beading
  • 5mx62mmx19mm = 0.0059cum.
  • Total = 0.00649cum. Say 6 cudm.
  • Add wastage @ 10% = 0.15sqm.
  • Add wastage @ 10% = 0.00059cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
7029Galvanised wire mesh of average width of aperture 1.4 mm and nominal dia. of wire 0.63 mmGalvanised wire mesh of average width of aperture 1.4 mm and nominal dia of wire 0.63 mmMaterialsqm1.69260.00439.40
9977Carriage of wire fabricMaterialL.S.1.822.274.13
1190Second class teak wood in planksMaterial10 cudm0.6791.00474.60
0112Carpenter 2nd classLabourday0.33816.00269.28
0114BeldarLabourday0.25736.00184.00
9999SundriesMaterialL.S.19.762.2744.86
TOTAL
1,416.27
Add 1 % Water charges on “W”
14.16
TOTAL
1,430.43
Add GST on “X” (multiplying factor 0.2127)
304.25
TOTAL
1,734.68
Add 15% CPOH on “Y”
260.20
TOTAL
1,994.88
Add Cess @ 1% on “Z”
19.95
Cost of 1.54 sqm.
2,014.83
Cost of 1 sqm.
1,308.33
Say
1,308.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 505. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.