CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing hard drawn steel wire fabric 75x25 mm mesh of weight not less than 7.75 Kg per sqm to window frames etc. including 62x19 mm beading of second class teak wood and priming coat with approved steel primer all complete

Item number
9.50
Analysis basis
Details of cost for a window of size 140x110cm
Priced inputs
7
Derived rate
1,641.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.50 Providing and fixing hard drawn steel wire fabric 75x25 mm mesh of weight not less than 7.75 Kg per sqm to window frames etc. including 62x19 mm beading of second class teak wood and priming coat with approved steel primer all complete — is derived from 7 priced inputs for a window and works out to ₹1,641.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • =1.54sqm.
  • Hard drawn steel wire fabric -20x60mm mesh
  • 3.2mm wide = 1.4x1.1m = 1.54sqm.+
  • Total = 1.69 sqm.
  • Priming coat
  • Area=1.40x1.10x1.00=1.54sqm
  • Second class teak wood beading
  • 5mx62mmx19mm = 0.0059cum.
  • Total = 0.00649cum. Say 6 cudm.
  • Add wastage @ 10% = 0.15sqm.
  • Add wastage @ 10% = 0.00059cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1021Hard drawn steel wire fabricHard drawn steel wire fabric 75 x 25 mm mesh of weight not less than 7.75 kg/sqmMaterialsqm1.69430.00726.70
9977Carriage of wire fabricMaterialL.S.1.822.274.13
Rate as per Item No.13.50.3 of SH:FINISHINGRate as per item 13.50.3Sub-analysissqm1.5467.40103.80
1190Second class teak wood in planksMaterial10 cudm0.6791.00474.60
0112Carpenter 2nd classLabourday0.33816.00269.28
0114BeldarLabourday0.25736.00184.00
9999SundriesMaterialL.S.19.762.2744.86
TOTAL
1,807.37
Add 1 % Water charges on “W-A”
17.04
TOTAL
1,824.41
Add GST on “X-A” (multiplying factor 0.2127)
365.97
TOTAL
2,190.38
Add 15% CPOH on “Y-A”
312.99
TOTAL
2,503.37
Add Cess @ 1% on “Z-A”
24.00
Cost of 1.54 sqm.
2,527.37
Cost of 1 sqm.
1,641.15
Say
1,641.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 504. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.